# Site weather record · Abidjan · February 2026

Site 5.3600, -4.0083. 28 of 28 days recorded, 28 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 66.1 mm against a pro-rata normal of 103 mm (64 % of normal; full-month normal 103 mm, 1991-2020).
- Rain days (1 mm or more): 18 against a pro-rata normal of 19.7.
- Heavy rain days (above the site's 1-in-10-day amount, 9 mm): 1; exceptional (above 1-in-100-day, 21 mm): 0.
- Days with gusts above the 1-in-10-day value (10 m/s): 2; days hotter than the 1-in-10-day maximum (33.4 °C): 1.
- Working hours lost to weather (caution or stop): outdoor labour 173 h, concrete pour 27 h, asphalt & surfacing 137 h, crane lifts 0 h, work at height 53 h, painting & coatings 115 h, earthworks 55 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-02-01 | ERA5 (final) | 3.2 | 1.8 | 31.3 | 9.8 | 31.6 | gust above 1-in-10-day | 2 | 7 | 1 | 8 | 6 | 3 | 7 |
| 2026-02-02 | ERA5 (final) | 2.6 | 1.8 | 31.1 | 9.2 | 31.5 |  | 1 | 7 | 1 | 8 | 5 | 2 | 7 |
| 2026-02-03 | ERA5 (final) | 18.7 | 7.0 | 29.8 | 7.8 | 30.0 | rain heavy (above 1-in-10-day) | 5 | 7 | 1 | 8 | 5 | 2 | 5 |
| 2026-02-04 | ERA5 (final) | 1.0 | 0.4 | 31.5 | 5.6 | 31.3 |  | 2 | 8 | 8 | 8 | 8 | 6 | 0 |
| 2026-02-05 | ERA5 (final) | 1.0 | 0.5 | 30.5 | 9.4 | 30.3 |  | 2 | 7 | 3 | 8 | 6 | 4 | 7 |
| 2026-02-06 | ERA5 (final) | 1.7 | 0.8 | 32.8 | 8.2 | 32.1 |  | 1 | 7 | 1 | 8 | 4 | 2 | 7 |
| 2026-02-07 | ERA5 (final) | 6.1 | 3.5 | 31.1 | 8.3 | 30.7 |  | 2 | 6 | 1 | 8 | 4 | 2 | 5 |
| 2026-02-08 | ERA5 (final) | 0.2 | 0.1 | 32.2 | 7.8 | 31.7 |  | 2 | 8 | 4 | 8 | 8 | 6 | 3 |
| 2026-02-09 | ERA5 (final) | 0.6 | 0.3 | 31.2 | 8.6 | 30.6 |  | 2 | 8 | 5 | 8 | 6 | 4 | 7 |
| 2026-02-10 | ERA5 (final) | 2.1 | 0.4 | 30.2 | 8.7 | 30.3 |  | 2 | 8 | 0 | 8 | 5 | 0 | 5 |
| 2026-02-11 | ERA5 (final) | 1.3 | 0.6 | 30.5 | 9.1 | 30.6 |  | 2 | 7 | 3 | 8 | 7 | 5 | 7 |
| 2026-02-12 | ERA5 (final) | 0.0 | 0.0 | 31.1 | 7.9 | 30.6 |  | 2 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-02-13 | ERA5 (final) | 0.4 | 0.2 | 30.7 | 7.8 | 29.8 |  | 3 | 8 | 4 | 8 | 7 | 5 | 8 |
| 2026-02-14 | ERA5 (final) | 5.3 | 3.7 | 30.3 | 8.1 | 29.9 |  | 2 | 7 | 1 | 8 | 3 | 1 | 6 |
| 2026-02-15 | ERA5 (final) | 0.2 | 0.1 | 30.6 | 7.7 | 30.2 |  | 2 | 8 | 4 | 8 | 8 | 6 | 6 |
| 2026-02-16 | ERA5 (final) | 0.6 | 0.6 | 31.5 | 7.9 | 32.1 |  | 2 | 7 | 7 | 8 | 7 | 5 | 7 |
| 2026-02-17 | ERA5 (final) | 1.8 | 0.6 | 31.3 | 8.0 | 31.4 |  | 1 | 7 | 3 | 8 | 4 | 2 | 7 |
| 2026-02-18 | ERA5 (final) | 0.0 | 0.0 | 32.8 | 7.1 | 31.5 |  | 1 | 7 | 8 | 8 | 8 | 6 | 8 |
| 2026-02-19 | ERA5 (final) | 0.2 | 0.1 | 32.1 | 8.3 | 31.6 |  | 2 | 7 | 2 | 8 | 8 | 6 | 8 |
| 2026-02-20 | ERA5 (final) | 0.0 | 0.0 | 33.5 | 8.9 | 31.9 | heat above 1-in-10-day | 1 | 5 | 8 | 8 | 8 | 6 | 8 |
| 2026-02-21 | ERA5 (final) | 1.1 | 0.8 | 33.3 | 7.8 | 32.2 |  | 1 | 7 | 3 | 8 | 6 | 4 | 7 |
| 2026-02-22 | ERA5 (final) | 2.1 | 0.9 | 33.1 | 8.6 | 31.8 |  | 1 | 6 | 1 | 8 | 6 | 4 | 6 |
| 2026-02-23 | ERA5 (final) | 1.7 | 0.6 | 32.1 | 8.2 | 31.4 |  | 1 | 7 | 0 | 8 | 6 | 4 | 6 |
| 2026-02-24 | ERA5 (final) | 2.9 | 0.7 | 31.6 | 10.2 | 31.5 | gust above 1-in-10-day | 1 | 5 | 0 | 8 | 4 | 3 | 4 |
| 2026-02-25 | ERA5 (final) | 1.6 | 1.2 | 32.1 | 8.5 | 32.0 |  | 2 | 7 | 2 | 8 | 7 | 5 | 7 |
| 2026-02-26 | ERA5 (final) | 7.8 | 3.3 | 31.4 | 8.2 | 31.4 |  | 3 | 6 | 0 | 8 | 4 | 0 | 3 |
| 2026-02-27 | ERA5 (final) | 0.5 | 0.2 | 32.2 | 8.5 | 31.8 |  | 1 | 8 | 2 | 8 | 6 | 5 | 3 |
| 2026-02-28 | ERA5 (final) | 1.4 | 0.7 | 30.8 | 9.5 | 29.9 |  | 2 | 7 | 6 | 8 | 7 | 5 | 7 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*