# Site weather record · Abuja · March 2026

Site 9.0765, 7.3986. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 6.0 mm against a pro-rata normal of 19 mm (31 % of normal; full-month normal 19 mm, 1991-2020).
- Rain days (1 mm or more): 2 against a pro-rata normal of 3.9.
- Heavy rain days (above the site's 1-in-10-day amount, 2 mm): 2; exceptional (above 1-in-100-day, 11 mm): 0.
- Days with gusts above the 1-in-10-day value (9 m/s): 4; days hotter than the 1-in-10-day maximum (37.7 °C): 4.
- Working hours lost to weather (caution or stop): outdoor labour 151 h, concrete pour 133 h, asphalt & surfacing 16 h, crane lifts 0 h, work at height 3 h, painting & coatings 21 h, earthworks 3 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-03-01 | ERA5 (final) | 0.0 | 0.0 | 35.8 | 7.4 | 28.0 |  | 8 | 0 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-02 | ERA5 (final) | 0.0 | 0.0 | 35.7 | 7.4 | 27.9 |  | 8 | 2 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-03 | ERA5 (final) | 0.0 | 0.0 | 35.9 | 7.9 | 28.2 |  | 6 | 1 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-04 | ERA5 (final) | 0.0 | 0.0 | 36.0 | 9.0 | 27.9 | gust above 1-in-10-day | 8 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-05 | ERA5 (final) | 0.0 | 0.0 | 36.1 | 5.5 | 30.8 |  | 2 | 5 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-06 | ERA5 (final) | 0.0 | 0.0 | 37.0 | 7.4 | 30.7 |  | 3 | 2 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-07 | ERA5 (final) | 0.0 | 0.0 | 38.0 | 8.3 | 28.8 | heat above 1-in-10-day | 3 | 1 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-08 | ERA5 (final) | 0.0 | 0.0 | 38.3 | 7.5 | 29.1 | heat above 1-in-10-day | 2 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-09 | ERA5 (final) | 0.0 | 0.0 | 38.6 | 5.9 | 32.1 | heat above 1-in-10-day | 1 | 5 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-10 | ERA5 (final) | 0.0 | 0.0 | 37.3 | 6.4 | 32.5 |  | 1 | 4 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-11 | ERA5 (final) | 0.0 | 0.0 | 35.2 | 8.2 | 31.1 |  | 3 | 4 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-12 | ERA5 (final) | 0.0 | 0.0 | 36.1 | 8.1 | 30.5 |  | 2 | 4 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-13 | ERA5 (final) | 1.6 | 0.7 | 36.3 | 7.1 | 31.1 | rain heavy (above 1-in-10-day) | 3 | 4 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-14 | ERA5 (final) | 0.0 | 0.0 | 37.5 | 8.1 | 30.3 |  | 2 | 4 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-15 | ERA5 (final) | 0.0 | 0.0 | 36.6 | 7.4 | 31.3 |  | 2 | 5 | 8 | 8 | 8 | 6 | 8 |
| 2026-03-16 | ERA5 (final) | 0.0 | 0.0 | 35.7 | 8.1 | 30.0 |  | 3 | 3 | 8 | 8 | 8 | 6 | 8 |
| 2026-03-17 | ERA5 (final) | 0.1 | 0.1 | 35.7 | 9.3 | 29.4 | gust above 1-in-10-day | 3 | 3 | 4 | 8 | 8 | 6 | 8 |
| 2026-03-18 | ERA5 (final) | 0.0 | 0.0 | 36.2 | 7.8 | 30.0 |  | 2 | 4 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-19 | ERA5 (final) | 0.0 | 0.0 | 36.7 | 5.6 | 31.7 |  | 2 | 5 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-20 | ERA5 (final) | 0.0 | 0.0 | 37.2 | 6.9 | 32.2 |  | 2 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-21 | ERA5 (final) | 0.0 | 0.0 | 37.0 | 7.3 | 31.6 |  | 3 | 1 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-22 | ERA5 (final) | 0.0 | 0.0 | 37.2 | 6.9 | 31.7 |  | 1 | 5 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-23 | ERA5 (final) | 0.1 | 0.1 | 36.9 | 7.3 | 32.4 |  | 1 | 7 | 5 | 8 | 8 | 7 | 8 |
| 2026-03-24 | ERA5 (final) | 0.0 | 0.0 | 37.2 | 9.0 | 31.1 | gust above 1-in-10-day | 2 | 5 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-25 | ERA5 (final) | 0.0 | 0.0 | 36.2 | 7.7 | 30.9 |  | 3 | 3 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-26 | ERA5 (final) | 0.0 | 0.0 | 33.8 | 7.9 | 30.5 |  | 3 | 8 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-27 | ERA5 (final) | 0.1 | 0.1 | 36.5 | 7.5 | 31.6 |  | 2 | 6 | 5 | 8 | 8 | 6 | 8 |
| 2026-03-28 | ERA5 (final) | 0.7 | 0.7 | 38.1 | 8.6 | 32.3 | heat above 1-in-10-day | 2 | 3 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-29 | ERA5 (final) | 0.0 | 0.0 | 35.0 | 10.2 | 29.6 | gust above 1-in-10-day | 3 | 3 | 8 | 8 | 8 | 7 | 8 |
| 2026-03-30 | ERA5 (final) | 0.8 | 0.3 | 35.2 | 8.4 | 29.4 |  | 3 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-03-31 | ERA5 (final) | 2.6 | 0.9 | 31.5 | 6.0 | 26.8 | rain heavy (above 1-in-10-day) | 8 | 6 | 2 | 8 | 5 | 4 | 5 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*