# Site weather record · Abuja · June 2026

Site 9.0765, 7.3986. 30 of 30 days recorded, 30 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 87.6 mm against a pro-rata normal of 195 mm (45 % of normal; full-month normal 195 mm, 1991-2020).
- Rain days (1 mm or more): 18 against a pro-rata normal of 23.2.
- Heavy rain days (above the site's 1-in-10-day amount, 16 mm): 0; exceptional (above 1-in-100-day, 30 mm): 0.
- Days with gusts above the 1-in-10-day value (8 m/s): 3; days hotter than the 1-in-10-day maximum (30.5 °C): 10.
- Working hours lost to weather (caution or stop): outdoor labour 79 h, concrete pour 8 h, asphalt & surfacing 70 h, crane lifts 0 h, work at height 16 h, painting & coatings 113 h, earthworks 44 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-06-01 | ERA5 (final) | 2.6 | 0.9 | 28.6 | 5.2 | 28.9 |  | 5 | 8 | 5 | 8 | 8 | 4 | 8 |
| 2026-06-02 | ERA5 (final) | 1.1 | 0.6 | 33.3 | 6.3 | 31.6 | heat above 1-in-10-day | 2 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-03 | ERA5 (final) | 0.2 | 0.1 | 27.6 | 5.8 | 27.4 |  | 8 | 8 | 6 | 8 | 8 | 5 | 8 |
| 2026-06-04 | ERA5 (final) | 0.3 | 0.1 | 31.0 | 7.4 | 29.4 | heat above 1-in-10-day | 3 | 8 | 7 | 8 | 8 | 6 | 8 |
| 2026-06-05 | ERA5 (final) | 12.0 | 3.2 | 29.2 | 5.9 | 28.7 |  | 7 | 6 | 2 | 8 | 4 | 1 | 6 |
| 2026-06-06 | ERA5 (final) | 1.1 | 0.8 | 29.0 | 9.0 | 27.9 | gust above 1-in-10-day | 8 | 7 | 7 | 8 | 7 | 4 | 0 |
| 2026-06-07 | ERA5 (final) | 3.0 | 0.9 | 30.6 | 5.3 | 29.5 | heat above 1-in-10-day | 2 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-06-08 | ERA5 (final) | 15.5 | 4.4 | 30.6 | 8.0 | 30.1 | gust above 1-in-10-day; heat above 1-in-10-day | 3 | 6 | 3 | 8 | 5 | 2 | 6 |
| 2026-06-09 | ERA5 (final) | 5.3 | 1.5 | 28.8 | 8.3 | 28.0 | gust above 1-in-10-day | 8 | 8 | 0 | 8 | 6 | 1 | 0 |
| 2026-06-10 | ERA5 (final) | 0.8 | 0.3 | 27.5 | 5.4 | 26.7 |  | 8 | 8 | 3 | 8 | 8 | 4 | 8 |
| 2026-06-11 | ERA5 (final) | 1.8 | 1.2 | 31.3 | 5.0 | 29.8 | heat above 1-in-10-day | 3 | 8 | 8 | 8 | 8 | 7 | 8 |
| 2026-06-12 | ERA5 (final) | 0.0 | 0.0 | 30.7 | 5.7 | 29.5 | heat above 1-in-10-day | 3 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-06-13 | ERA5 (final) | 0.6 | 0.6 | 29.3 | 7.6 | 26.1 |  | 8 | 6 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-14 | ERA5 (final) | 0.0 | 0.0 | 27.8 | 5.9 | 26.4 |  | 8 | 8 | 8 | 8 | 8 | 4 | 8 |
| 2026-06-15 | ERA5 (final) | 0.7 | 0.3 | 29.7 | 6.4 | 29.5 |  | 5 | 8 | 5 | 8 | 8 | 5 | 8 |
| 2026-06-16 | ERA5 (final) | 0.0 | 0.0 | 31.3 | 6.1 | 29.2 | heat above 1-in-10-day | 3 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-17 | ERA5 (final) | 0.2 | 0.1 | 28.2 | 6.4 | 27.1 |  | 8 | 8 | 4 | 8 | 8 | 4 | 8 |
| 2026-06-18 | ERA5 (final) | 1.3 | 1.0 | 31.8 | 6.7 | 29.8 | heat above 1-in-10-day | 3 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-06-19 | ERA5 (final) | 12.5 | 8.6 | 32.7 | 6.0 | 30.5 | heat above 1-in-10-day | 3 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-20 | ERA5 (final) | 6.8 | 2.3 | 28.7 | 6.4 | 28.6 |  | 5 | 7 | 3 | 8 | 4 | 0 | 0 |
| 2026-06-21 | ERA5 (final) | 1.3 | 0.3 | 28.9 | 6.5 | 27.1 |  | 8 | 8 | 8 | 8 | 8 | 5 | 0 |
| 2026-06-22 | ERA5 (final) | 1.7 | 0.6 | 28.5 | 6.2 | 28.4 |  | 6 | 8 | 4 | 8 | 8 | 5 | 8 |
| 2026-06-23 | ERA5 (final) | 0.0 | 0.0 | 28.8 | 6.6 | 27.8 |  | 8 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-06-24 | ERA5 (final) | 0.8 | 0.5 | 30.7 | 5.6 | 30.3 | heat above 1-in-10-day | 3 | 8 | 6 | 8 | 8 | 5 | 8 |
| 2026-06-25 | ERA5 (final) | 5.9 | 1.8 | 28.3 | 6.2 | 28.6 |  | 5 | 8 | 6 | 8 | 8 | 5 | 8 |
| 2026-06-26 | ERA5 (final) | 1.2 | 1.0 | 30.4 | 6.1 | 30.1 |  | 5 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-27 | ERA5 (final) | 0.0 | 0.0 | 30.1 | 6.1 | 28.4 |  | 6 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-28 | ERA5 (final) | 6.7 | 3.6 | 28.6 | 6.7 | 29.1 |  | 5 | 8 | 1 | 8 | 8 | 3 | 8 |
| 2026-06-29 | ERA5 (final) | 2.7 | 1.4 | 28.2 | 5.9 | 28.1 |  | 7 | 8 | 3 | 8 | 8 | 2 | 0 |
| 2026-06-30 | ERA5 (final) | 1.5 | 0.3 | 28.0 | 5.9 | 28.5 |  | 5 | 8 | 1 | 8 | 6 | 1 | 8 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*