# Site weather record · Arua · November 2026

Site 3.0201, 30.9111. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 10.5 mm against a pro-rata normal of 31 mm (34 % of normal; full-month normal 72 mm, 1991-2020).
- Rain days (1 mm or more): 5 against a pro-rata normal of 6.0.
- Heavy rain days (above the site's 1-in-10-day amount, 7 mm): 0; exceptional (above 1-in-100-day, 15 mm): 0.
- Days with gusts above the 1-in-10-day value (12 m/s): 0; days hotter than the 1-in-10-day maximum (29.3 °C): 5.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 42 h, asphalt & surfacing 24 h, crane lifts 0 h, work at height 16 h, painting & coatings 24 h, earthworks 7 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 0.1 | 0.1 | 29.0 | 8.5 | 26.6 |  | 8 | 5 | 8 | 8 | 8 | 7 | 8 |
| 2026-11-02 | ERA5 (final) | 0.0 | 0.0 | 29.0 | 9.2 | 26.7 |  | 8 | 8 | 8 | 8 | 8 | 7 | 8 |
| 2026-11-03 | ERA5 (final) | 0.0 | 0.0 | 29.5 | 7.9 | 27.0 | heat above 1-in-10-day | 8 | 5 | 8 | 8 | 8 | 7 | 8 |
| 2026-11-04 | ERA5 (final) | 0.0 | 0.0 | 29.9 | 10.0 | 26.4 | heat above 1-in-10-day | 8 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-11-11 | ERA5 (final) | 1.0 | 0.7 | 27.4 | 7.8 | 25.4 |  | 8 | 7 | 6 | 8 | 7 | 5 | 7 |
| 2026-11-12 | ERA5 (final) | 0.0 | 0.0 | 23.3 | 5.1 | 21.4 |  | 8 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-11-13 | model analysis (preliminary) | 4.6 | 1.9 | 26.4 | 7.4 | 26.0 |  | 8 | 6 | 3 | 8 | 5 | 3 | 5 |
| 2026-11-14 | model analysis (preliminary) | 0.6 | 0.3 | 26.7 | 8.6 | 25.2 |  | 8 | 7 | 6 | 8 | 7 | 5 | 8 |
| 2026-11-15 | model analysis (preliminary) | 1.2 | 0.4 | 27.2 | 12.0 | 24.6 |  | 8 | 4 | 5 | 8 | 3 | 4 | 6 |
| 2026-11-16 | model analysis (preliminary) | 0.4 | 0.3 | 28.5 | 10.9 | 25.4 |  | 8 | 2 | 8 | 8 | 8 | 7 | 8 |
| 2026-11-17 | model analysis (preliminary) | 0.4 | 0.2 | 30.3 | 11.8 | 25.8 | heat above 1-in-10-day | 8 | 2 | 7 | 8 | 5 | 8 | 8 |
| 2026-11-18 | model analysis (preliminary) | 1.2 | 0.5 | 29.9 | 11.5 | 24.9 | heat above 1-in-10-day | 8 | 3 | 2 | 8 | 6 | 6 | 8 |
| 2026-11-19 | model analysis (preliminary) | 1.0 | 0.4 | 30.0 | 10.3 | 25.8 | heat above 1-in-10-day | 8 | 2 | 3 | 8 | 7 | 7 | 7 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*