# Site weather record · Arusha · November 2026

Site -3.3869, 36.6830. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 57.7 mm against a pro-rata normal of 25 mm (233 % of normal; full-month normal 57 mm, 1991-2020).
- Rain days (1 mm or more): 9 against a pro-rata normal of 4.9.
- Heavy rain days (above the site's 1-in-10-day amount, 4 mm): 6; exceptional (above 1-in-100-day, 23 mm): 0.
- Days with gusts above the 1-in-10-day value (11 m/s): 0; days hotter than the 1-in-10-day maximum (29.2 °C): 3.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 30 h, asphalt & surfacing 87 h, crane lifts 0 h, work at height 43 h, painting & coatings 55 h, earthworks 27 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 0.9 | 0.2 | 27.6 | 8.8 | 24.1 |  | 8 | 6 | 1 | 8 | 4 | 3 | 8 |
| 2026-11-02 | ERA5 (final) | 1.3 | 0.3 | 29.4 | 8.4 | 25.9 | heat above 1-in-10-day | 8 | 6 | 0 | 8 | 4 | 3 | 7 |
| 2026-11-03 | ERA5 (final) | 0.3 | 0.1 | 29.0 | 9.3 | 24.8 |  | 8 | 5 | 3 | 8 | 8 | 7 | 8 |
| 2026-11-04 | ERA5 (final) | 0.3 | 0.1 | 30.0 | 9.9 | 24.4 | heat above 1-in-10-day | 8 | 5 | 3 | 8 | 8 | 7 | 8 |
| 2026-11-05 | ERA5 (final) | 0.5 | 0.2 | 29.8 | 9.3 | 23.8 | heat above 1-in-10-day | 8 | 4 | 3 | 8 | 7 | 7 | 8 |
| 2026-11-12 | ERA5 (final) | 2.8 | 0.8 | 27.6 | 8.5 | 24.5 |  | 8 | 8 | 3 | 8 | 8 | 8 | 8 |
| 2026-11-13 | model analysis (preliminary) | 10.9 | 2.5 | 25.9 | 6.5 | 22.9 | rain heavy (above 1-in-10-day) | 8 | 3 | 0 | 8 | 1 | 0 | 1 |
| 2026-11-14 | model analysis (preliminary) | 9.9 | 4.9 | 25.0 | 8.3 | 24.9 | rain heavy (above 1-in-10-day) | 8 | 6 | 1 | 8 | 3 | 2 | 4 |
| 2026-11-15 | model analysis (preliminary) | 10.7 | 6.5 | 25.7 | 7.6 | 24.4 | rain heavy (above 1-in-10-day) | 8 | 7 | 0 | 8 | 1 | 0 | 5 |
| 2026-11-16 | model analysis (preliminary) | 9.2 | 3.5 | 26.0 | 8.6 | 25.1 | rain heavy (above 1-in-10-day) | 8 | 6 | 2 | 8 | 6 | 4 | 5 |
| 2026-11-17 | model analysis (preliminary) | 5.1 | 1.1 | 24.9 | 9.0 | 24.4 | rain heavy (above 1-in-10-day) | 8 | 6 | 0 | 8 | 1 | 1 | 3 |
| 2026-11-18 | model analysis (preliminary) | 3.8 | 1.3 | 26.3 | 9.7 | 24.1 | rain heavy (above 1-in-10-day) | 8 | 6 | 0 | 8 | 4 | 2 | 6 |
| 2026-11-19 | model analysis (preliminary) | 2.0 | 0.7 | 26.4 | 11.0 | 23.8 |  | 8 | 6 | 1 | 8 | 6 | 5 | 6 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*