# Site weather record · Dammam · November 2026

Site 26.4207, 50.0888. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 0.3 mm against a pro-rata normal of 8 mm (4 % of normal; full-month normal 18 mm, 1991-2020).
- Rain days (1 mm or more): 0 against a pro-rata normal of 1.0.
- Heavy rain days (above the site's 1-in-10-day amount, 0 mm): 0; exceptional (above 1-in-100-day, 13 mm): 0.
- Days with gusts above the 1-in-10-day value (13 m/s): 2; days hotter than the 1-in-10-day maximum (31.0 °C): 5.
- Working hours lost to weather (caution or stop): outdoor labour 28 h, concrete pour 60 h, asphalt & surfacing 7 h, crane lifts 1 h, work at height 25 h, painting & coatings 7 h, earthworks 1 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 0.0 | 0.0 | 34.2 | 7.0 | 29.6 | heat above 1-in-10-day | 4 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-02 | ERA5 (final) | 0.0 | 0.0 | 34.1 | 6.9 | 30.0 | heat above 1-in-10-day | 1 | 4 | 9 | 9 | 9 | 8 | 9 |
| 2026-11-03 | ERA5 (final) | 0.0 | 0.0 | 35.3 | 6.9 | 28.4 | heat above 1-in-10-day | 6 | 5 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-04 | ERA5 (final) | 0.0 | 0.0 | 32.9 | 9.7 | 28.6 | heat above 1-in-10-day | 3 | 2 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-05 | ERA5 (final) | 0.3 | 0.3 | 33.3 | 10.3 | 29.0 | heat above 1-in-10-day | 3 | 3 | 8 | 9 | 8 | 6 | 8 |
| 2026-11-12 | ERA5 (final) | 0.0 | 0.0 | 23.7 | 12.9 | 21.4 | gust above 1-in-10-day | 9 | 1 | 3 | 8 | 1 | 9 | 9 |
| 2026-11-13 | model analysis (preliminary) | 0.0 | 0.0 | 23.9 | 12.0 | 21.1 |  | 9 | 4 | 9 | 9 | 5 | 9 | 9 |
| 2026-11-14 | model analysis (preliminary) | 0.0 | 0.0 | 23.7 | 12.7 | 19.1 | gust above 1-in-10-day | 9 | 3 | 9 | 9 | 2 | 9 | 9 |
| 2026-11-15 | model analysis (preliminary) | 0.0 | 0.0 | 25.8 | 11.7 | 21.4 |  | 9 | 3 | 9 | 9 | 4 | 9 | 9 |
| 2026-11-16 | model analysis (preliminary) | 0.0 | 0.0 | 27.0 | 10.3 | 22.8 |  | 9 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-17 | model analysis (preliminary) | 0.0 | 0.0 | 27.8 | 7.4 | 25.3 |  | 9 | 9 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-18 | model analysis (preliminary) | 0.0 | 0.0 | 28.8 | 6.3 | 26.9 |  | 9 | 9 | 9 | 9 | 9 | 8 | 9 |
| 2026-11-19 | model analysis (preliminary) | 0.0 | 0.0 | 29.7 | 6.0 | 27.8 |  | 9 | 8 | 9 | 9 | 9 | 7 | 9 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*