# Site weather record · Dubai · March 2026

Site 25.2048, 55.2708. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 148.7 mm against a pro-rata normal of 17 mm (899 % of normal; full-month normal 17 mm, 1991-2020).
- Rain days (1 mm or more): 7 against a pro-rata normal of 2.0.
- Heavy rain days (above the site's 1-in-10-day amount, 0 mm): 6; exceptional (above 1-in-100-day, 15 mm): 4.
- Days with gusts above the 1-in-10-day value (15 m/s): 3; days hotter than the 1-in-10-day maximum (34.8 °C): 3.
- Working hours lost to weather (caution or stop): outdoor labour 2 h, concrete pour 184 h, asphalt & surfacing 82 h, crane lifts 17 h, work at height 78 h, painting & coatings 73 h, earthworks 54 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-03-01 | ERA5 (final) | 0.0 | 0.0 | 34.2 | 7.2 | 26.7 |  | 9 | 2 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-02 | ERA5 (final) | 0.0 | 0.0 | 34.7 | 13.5 | 25.6 |  | 9 | 0 | 7 | 7 | 4 | 9 | 9 |
| 2026-03-03 | ERA5 (final) | 0.0 | 0.0 | 34.5 | 10.9 | 25.8 |  | 9 | 0 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-04 | ERA5 (final) | 0.0 | 0.0 | 30.5 | 13.1 | 26.4 |  | 9 | 2 | 9 | 9 | 6 | 9 | 9 |
| 2026-03-05 | ERA5 (final) | 0.0 | 0.0 | 27.3 | 10.9 | 24.3 |  | 9 | 5 | 9 | 9 | 9 | 6 | 9 |
| 2026-03-06 | ERA5 (final) | 0.0 | 0.0 | 25.3 | 10.5 | 21.9 |  | 9 | 4 | 9 | 9 | 9 | 8 | 9 |
| 2026-03-07 | ERA5 (final) | 0.0 | 0.0 | 27.9 | 9.4 | 22.9 |  | 9 | 4 | 9 | 9 | 9 | 7 | 9 |
| 2026-03-08 | ERA5 (final) | 0.0 | 0.0 | 27.1 | 12.3 | 22.5 |  | 9 | 5 | 8 | 9 | 7 | 6 | 9 |
| 2026-03-09 | ERA5 (final) | 0.1 | 0.1 | 28.9 | 8.2 | 24.4 |  | 9 | 5 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-10 | ERA5 (final) | 0.2 | 0.1 | 29.4 | 11.3 | 24.3 |  | 9 | 4 | 1 | 9 | 9 | 6 | 9 |
| 2026-03-11 | ERA5 (final) | 1.2 | 0.8 | 30.7 | 8.9 | 25.9 | rain heavy (above 1-in-10-day) | 9 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-12 | ERA5 (final) | 0.5 | 0.3 | 29.7 | 7.8 | 24.8 | rain heavy (above 1-in-10-day) | 9 | 7 | 6 | 9 | 7 | 5 | 8 |
| 2026-03-13 | ERA5 (final) | 0.3 | 0.2 | 31.7 | 7.2 | 27.1 | rain heavy (above 1-in-10-day) | 9 | 3 | 3 | 9 | 8 | 6 | 9 |
| 2026-03-14 | ERA5 (final) | 0.0 | 0.0 | 32.6 | 9.6 | 26.7 |  | 9 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-03-15 | ERA5 (final) | 0.0 | 0.0 | 35.4 | 9.0 | 28.2 | heat above 1-in-10-day | 8 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-16 | ERA5 (final) | 0.0 | 0.0 | 36.0 | 12.0 | 26.5 | heat above 1-in-10-day | 9 | 2 | 9 | 9 | 6 | 9 | 9 |
| 2026-03-17 | ERA5 (final) | 0.0 | 0.0 | 35.5 | 11.6 | 26.4 | heat above 1-in-10-day | 9 | 0 | 9 | 9 | 6 | 9 | 9 |
| 2026-03-18 | ERA5 (final) | 0.1 | 0.1 | 30.7 | 13.0 | 25.1 |  | 9 | 3 | 8 | 9 | 5 | 7 | 9 |
| 2026-03-19 | ERA5 (final) | 0.0 | 0.0 | 31.0 | 6.5 | 25.6 |  | 9 | 5 | 9 | 9 | 9 | 7 | 9 |
| 2026-03-20 | ERA5 (final) | 0.0 | 0.0 | 33.9 | 13.0 | 25.9 |  | 9 | 1 | 9 | 9 | 8 | 9 | 9 |
| 2026-03-21 | ERA5 (final) | 1.5 | 0.4 | 31.4 | 14.7 | 26.9 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 9 | 2 | 0 | 7 | 4 | 5 | 8 |
| 2026-03-22 | ERA5 (final) | 0.0 | 0.0 | 32.4 | 7.3 | 28.1 |  | 8 | 3 | 9 | 9 | 9 | 7 | 9 |
| 2026-03-23 | ERA5 (final) | 26.9 | 4.6 | 26.1 | 8.7 | 24.0 | rain exceptional (above 1-in-100-day) | 9 | 4 | 1 | 9 | 1 | 0 | 3 |
| 2026-03-24 | ERA5 (final) | 21.8 | 7.5 | 25.6 | 11.7 | 25.4 | rain exceptional (above 1-in-100-day) | 9 | 2 | 0 | 9 | 1 | 0 | 0 |
| 2026-03-25 | ERA5 (final) | 34.1 | 7.6 | 25.4 | 16.4 | 24.8 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 9 | 3 | 1 | 6 | 2 | 0 | 0 |
| 2026-03-26 | ERA5 (final) | 4.0 | 1.6 | 29.6 | 12.4 | 27.6 | rain heavy (above 1-in-10-day) | 9 | 3 | 3 | 9 | 6 | 5 | 0 |
| 2026-03-27 | ERA5 (final) | 57.3 | 13.3 | 26.0 | 14.3 | 24.6 | rain exceptional (above 1-in-100-day) | 9 | 3 | 0 | 5 | 1 | 0 | 0 |
| 2026-03-28 | ERA5 (final) | 0.0 | 0.0 | 24.3 | 12.3 | 21.4 |  | 9 | 2 | 9 | 9 | 4 | 9 | 0 |
| 2026-03-29 | ERA5 (final) | 0.0 | 0.0 | 25.4 | 16.6 | 21.4 | gust above 1-in-10-day | 9 | 1 | 2 | 3 | 2 | 9 | 9 |
| 2026-03-30 | ERA5 (final) | 0.0 | 0.0 | 25.5 | 11.2 | 22.0 |  | 9 | 3 | 9 | 9 | 8 | 9 | 9 |
| 2026-03-31 | ERA5 (final) | 0.7 | 0.3 | 25.3 | 7.2 | 24.6 | rain heavy (above 1-in-10-day) | 9 | 8 | 4 | 9 | 7 | 6 | 8 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*