# Site weather record · Gaborone · April 2026

Site -24.6282, 25.9231. 30 of 30 days recorded, 30 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 92.9 mm against a pro-rata normal of 30 mm (308 % of normal; full-month normal 30 mm, 1991-2020).
- Rain days (1 mm or more): 11 against a pro-rata normal of 4.5.
- Heavy rain days (above the site's 1-in-10-day amount, 2 mm): 8; exceptional (above 1-in-100-day, 16 mm): 2.
- Days with gusts above the 1-in-10-day value (11 m/s): 8; days hotter than the 1-in-10-day maximum (31.4 °C): 0.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 36 h, asphalt & surfacing 107 h, crane lifts 5 h, work at height 49 h, painting & coatings 92 h, earthworks 63 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-04-01 | ERA5 (final) | 0.5 | 0.5 | 28.2 | 8.6 | 26.3 |  | 8 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-04-02 | ERA5 (final) | 0.0 | 0.0 | 28.8 | 6.4 | 26.7 |  | 8 | 8 | 8 | 8 | 8 | 7 | 8 |
| 2026-04-03 | ERA5 (final) | 0.0 | 0.0 | 26.1 | 8.3 | 23.1 |  | 8 | 8 | 8 | 8 | 8 | 7 | 8 |
| 2026-04-04 | ERA5 (final) | 0.0 | 0.0 | 28.6 | 5.9 | 27.3 |  | 8 | 8 | 8 | 8 | 8 | 8 | 8 |
| 2026-04-05 | ERA5 (final) | 0.0 | 0.0 | 30.6 | 5.9 | 26.6 |  | 8 | 5 | 8 | 8 | 8 | 8 | 8 |
| 2026-04-06 | ERA5 (final) | 0.0 | 0.0 | 29.4 | 6.2 | 26.7 |  | 8 | 8 | 8 | 8 | 8 | 8 | 8 |
| 2026-04-07 | ERA5 (final) | 5.4 | 1.9 | 27.0 | 12.4 | 24.1 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 8 | 2 | 3 | 8 | 5 | 7 | 7 |
| 2026-04-08 | ERA5 (final) | 0.5 | 0.1 | 25.5 | 12.3 | 22.3 | gust above 1-in-10-day | 8 | 4 | 2 | 8 | 5 | 6 | 3 |
| 2026-04-09 | ERA5 (final) | 0.0 | 0.0 | 25.6 | 8.0 | 22.9 |  | 8 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-04-10 | ERA5 (final) | 0.0 | 0.0 | 29.3 | 4.7 | 27.5 |  | 8 | 8 | 8 | 8 | 8 | 6 | 8 |
| 2026-04-11 | ERA5 (final) | 0.0 | 0.0 | 29.9 | 6.5 | 26.9 |  | 8 | 5 | 8 | 8 | 8 | 7 | 8 |
| 2026-04-12 | ERA5 (final) | 0.2 | 0.2 | 26.9 | 5.8 | 26.5 |  | 8 | 8 | 6 | 8 | 7 | 5 | 8 |
| 2026-04-13 | ERA5 (final) | 5.0 | 0.6 | 25.2 | 9.0 | 24.2 | rain heavy (above 1-in-10-day) | 8 | 7 | 0 | 8 | 5 | 5 | 6 |
| 2026-04-14 | ERA5 (final) | 2.3 | 1.0 | 25.6 | 11.6 | 23.5 | gust above 1-in-10-day | 8 | 6 | 4 | 8 | 5 | 5 | 6 |
| 2026-04-15 | ERA5 (final) | 13.2 | 3.3 | 21.3 | 6.5 | 20.9 | rain heavy (above 1-in-10-day) | 8 | 3 | 0 | 8 | 2 | 0 | 0 |
| 2026-04-16 | ERA5 (final) | 2.6 | 0.6 | 25.8 | 7.1 | 24.7 | rain heavy (above 1-in-10-day) | 8 | 8 | 0 | 8 | 8 | 5 | 5 |
| 2026-04-17 | ERA5 (final) | 6.7 | 3.5 | 24.2 | 12.9 | 23.8 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 8 | 8 | 4 | 7 | 3 | 3 | 7 |
| 2026-04-18 | ERA5 (final) | 16.0 | 4.3 | 26.7 | 9.6 | 24.9 | rain exceptional (above 1-in-100-day) | 8 | 7 | 0 | 8 | 6 | 3 | 0 |
| 2026-04-19 | ERA5 (final) | 3.3 | 1.3 | 26.9 | 14.1 | 25.0 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 8 | 5 | 1 | 7 | 3 | 4 | 0 |
| 2026-04-20 | ERA5 (final) | 0.1 | 0.1 | 28.7 | 6.8 | 26.5 |  | 8 | 8 | 6 | 8 | 8 | 6 | 8 |
| 2026-04-21 | ERA5 (final) | 0.7 | 0.5 | 27.2 | 11.4 | 25.1 | gust above 1-in-10-day | 8 | 7 | 5 | 8 | 7 | 5 | 7 |
| 2026-04-22 | ERA5 (final) | 26.5 | 4.3 | 23.4 | 7.8 | 23.3 | rain exceptional (above 1-in-100-day) | 8 | 5 | 0 | 8 | 5 | 0 | 0 |
| 2026-04-23 | ERA5 (final) | 3.3 | 0.6 | 20.4 | 12.4 | 18.9 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 8 | 8 | 1 | 8 | 4 | 0 | 0 |
| 2026-04-24 | ERA5 (final) | 4.2 | 0.6 | 18.6 | 10.4 | 16.8 | rain heavy (above 1-in-10-day) | 8 | 7 | 0 | 8 | 5 | 0 | 0 |
| 2026-04-25 | ERA5 (final) | 0.5 | 0.2 | 20.1 | 7.9 | 19.0 |  | 8 | 8 | 3 | 8 | 7 | 0 | 8 |
| 2026-04-26 | ERA5 (final) | 0.0 | 0.0 | 25.4 | 4.7 | 24.5 |  | 8 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-04-27 | ERA5 (final) | 0.4 | 0.3 | 28.7 | 9.0 | 26.0 |  | 8 | 5 | 5 | 8 | 8 | 6 | 8 |
| 2026-04-28 | ERA5 (final) | 0.0 | 0.0 | 27.0 | 5.7 | 22.9 |  | 8 | 8 | 8 | 8 | 8 | 8 | 8 |
| 2026-04-29 | ERA5 (final) | 0.7 | 0.4 | 23.8 | 10.4 | 22.2 |  | 8 | 8 | 5 | 8 | 7 | 6 | 8 |
| 2026-04-30 | ERA5 (final) | 0.8 | 0.2 | 22.9 | 13.7 | 20.3 | gust above 1-in-10-day | 8 | 8 | 0 | 5 | 3 | 6 | 8 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*