# Site weather record · Jeddah · July 2026

Site 21.4858, 39.1925. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 0.0 mm against a pro-rata normal of 0 mm (normal under 1 mm, so no percentage; full-month normal 0 mm, 1991-2020).
- Rain days (1 mm or more): 0 against a pro-rata normal of 0.0.
- Heavy rain days (above the site's 1-in-10-day amount, 0 mm): 0; exceptional (above 1-in-100-day, 0 mm): 31.
- Days with gusts above the 1-in-10-day value (14 m/s): 8; days hotter than the 1-in-10-day maximum (37.0 °C): 3.
- Working hours lost to weather (caution or stop): outdoor labour 250 h, concrete pour 236 h, asphalt & surfacing 38 h, crane lifts 28 h, work at height 60 h, painting & coatings 9 h, earthworks 0 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-07-01 | ERA5 (final) | 0.0 | 0.0 | 34.9 | 13.7 | 30.7 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 1 | 1 | 5 | 6 | 5 | 9 | 9 |
| 2026-07-02 | ERA5 (final) | 0.0 | 0.0 | 34.6 | 13.9 | 30.9 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 1 | 1 | 6 | 6 | 5 | 9 | 9 |
| 2026-07-03 | ERA5 (final) | 0.0 | 0.0 | 34.2 | 10.6 | 31.2 | rain exceptional (above 1-in-100-day) | 1 | 2 | 9 | 9 | 9 | 8 | 9 |
| 2026-07-04 | ERA5 (final) | 0.0 | 0.0 | 34.8 | 12.0 | 31.3 | rain exceptional (above 1-in-100-day) | 1 | 2 | 8 | 9 | 7 | 8 | 9 |
| 2026-07-05 | ERA5 (final) | 0.0 | 0.0 | 35.5 | 11.9 | 31.7 | rain exceptional (above 1-in-100-day) | 1 | 1 | 8 | 9 | 7 | 9 | 9 |
| 2026-07-06 | ERA5 (final) | 0.0 | 0.0 | 36.4 | 12.8 | 32.0 | rain exceptional (above 1-in-100-day) | 1 | 0 | 9 | 9 | 5 | 9 | 9 |
| 2026-07-07 | ERA5 (final) | 0.0 | 0.0 | 35.6 | 11.1 | 31.9 | rain exceptional (above 1-in-100-day) | 1 | 2 | 9 | 9 | 7 | 9 | 9 |
| 2026-07-08 | ERA5 (final) | 0.0 | 0.0 | 36.0 | 13.4 | 31.8 | rain exceptional (above 1-in-100-day) | 0 | 1 | 7 | 8 | 7 | 9 | 9 |
| 2026-07-09 | ERA5 (final) | 0.0 | 0.0 | 35.9 | 13.9 | 30.5 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 1 | 0 | 5 | 6 | 5 | 9 | 9 |
| 2026-07-10 | ERA5 (final) | 0.0 | 0.0 | 35.6 | 15.7 | 29.7 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 2 | 0 | 5 | 5 | 4 | 9 | 9 |
| 2026-07-11 | ERA5 (final) | 0.0 | 0.0 | 34.4 | 15.1 | 29.7 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 2 | 0 | 4 | 5 | 4 | 9 | 9 |
| 2026-07-12 | ERA5 (final) | 0.0 | 0.0 | 34.5 | 9.8 | 30.8 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-07-13 | ERA5 (final) | 0.0 | 0.0 | 34.4 | 10.4 | 30.8 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-07-14 | ERA5 (final) | 0.0 | 0.0 | 34.7 | 10.0 | 30.9 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-07-15 | ERA5 (final) | 0.0 | 0.0 | 34.6 | 9.3 | 31.0 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-07-16 | ERA5 (final) | 0.0 | 0.0 | 34.8 | 10.7 | 31.2 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-07-17 | ERA5 (final) | 0.0 | 0.0 | 35.3 | 12.5 | 30.7 | rain exceptional (above 1-in-100-day) | 0 | 1 | 6 | 9 | 5 | 9 | 9 |
| 2026-07-18 | ERA5 (final) | 0.0 | 0.0 | 36.3 | 11.0 | 30.6 | rain exceptional (above 1-in-100-day) | 1 | 1 | 9 | 9 | 8 | 9 | 9 |
| 2026-07-19 | ERA5 (final) | 0.0 | 0.0 | 36.1 | 14.4 | 30.6 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 1 | 0 | 5 | 6 | 5 | 9 | 9 |
| 2026-07-20 | ERA5 (final) | 0.0 | 0.0 | 38.9 | 17.0 | 31.4 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day; heat above 1-in-10-day | 1 | 0 | 5 | 5 | 5 | 9 | 9 |
| 2026-07-21 | ERA5 (final) | 0.0 | 0.0 | 40.7 | 16.0 | 31.8 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day; heat above 1-in-10-day | 1 | 0 | 6 | 6 | 5 | 9 | 9 |
| 2026-07-22 | ERA5 (final) | 0.0 | 0.0 | 35.0 | 10.0 | 31.7 | rain exceptional (above 1-in-100-day) | 0 | 0 | 9 | 9 | 9 | 9 | 9 |
| 2026-07-23 | ERA5 (final) | 0.0 | 0.0 | 34.6 | 8.0 | 31.3 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-07-24 | ERA5 (final) | 0.0 | 0.0 | 35.6 | 8.6 | 31.5 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-07-25 | ERA5 (final) | 0.0 | 0.0 | 36.3 | 8.3 | 31.4 | rain exceptional (above 1-in-100-day) | 1 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-07-26 | ERA5 (final) | 0.0 | 0.0 | 36.2 | 9.3 | 30.5 | rain exceptional (above 1-in-100-day) | 2 | 0 | 9 | 9 | 9 | 9 | 9 |
| 2026-07-27 | ERA5 (final) | 0.0 | 0.0 | 36.9 | 11.7 | 31.1 | rain exceptional (above 1-in-100-day) | 1 | 2 | 9 | 9 | 7 | 9 | 9 |
| 2026-07-28 | ERA5 (final) | 0.0 | 0.0 | 36.5 | 11.8 | 32.9 | rain exceptional (above 1-in-100-day) | 0 | 2 | 9 | 9 | 5 | 7 | 9 |
| 2026-07-29 | ERA5 (final) | 0.0 | 0.0 | 36.6 | 11.2 | 31.7 | rain exceptional (above 1-in-100-day) | 0 | 1 | 9 | 9 | 6 | 9 | 9 |
| 2026-07-30 | ERA5 (final) | 0.0 | 0.0 | 37.3 | 10.6 | 30.3 | rain exceptional (above 1-in-100-day); heat above 1-in-10-day | 1 | 1 | 9 | 9 | 9 | 9 | 9 |
| 2026-07-31 | ERA5 (final) | 0.0 | 0.0 | 36.6 | 9.0 | 31.0 | rain exceptional (above 1-in-100-day) | 1 | 1 | 9 | 9 | 9 | 9 | 9 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*