# Site weather record · Jeddah · November 2026

Site 21.4858, 39.1925. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 5.6 mm against a pro-rata normal of 11 mm (50 % of normal; full-month normal 26 mm, 1991-2020).
- Rain days (1 mm or more): 2 against a pro-rata normal of 1.0.
- Heavy rain days (above the site's 1-in-10-day amount, 0 mm): 3; exceptional (above 1-in-100-day, 22 mm): 0.
- Days with gusts above the 1-in-10-day value (12 m/s): 0; days hotter than the 1-in-10-day maximum (32.8 °C): 10.
- Working hours lost to weather (caution or stop): outdoor labour 79 h, concrete pour 59 h, asphalt & surfacing 15 h, crane lifts 0 h, work at height 7 h, painting & coatings 15 h, earthworks 4 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 0.0 | 0.0 | 33.6 | 9.0 | 29.9 | heat above 1-in-10-day | 2 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-02 | ERA5 (final) | 0.0 | 0.0 | 33.4 | 8.9 | 30.0 | heat above 1-in-10-day | 2 | 4 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-03 | ERA5 (final) | 0.0 | 0.0 | 34.6 | 10.8 | 29.8 | heat above 1-in-10-day | 3 | 2 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-04 | ERA5 (final) | 0.0 | 0.0 | 32.9 | 9.7 | 29.9 | heat above 1-in-10-day | 3 | 5 | 9 | 9 | 9 | 8 | 9 |
| 2026-11-05 | ERA5 (final) | 0.0 | 0.0 | 32.7 | 9.3 | 30.8 |  | 1 | 5 | 9 | 9 | 9 | 7 | 9 |
| 2026-11-12 | ERA5 (final) | 0.0 | 0.0 | 30.8 | 7.8 | 29.0 |  | 6 | 5 | 9 | 9 | 9 | 8 | 9 |
| 2026-11-13 | model analysis (preliminary) | 3.0 | 1.1 | 32.7 | 11.5 | 29.5 | rain heavy (above 1-in-10-day) | 3 | 6 | 4 | 9 | 7 | 6 | 8 |
| 2026-11-14 | model analysis (preliminary) | 0.0 | 0.0 | 32.8 | 10.0 | 29.7 | heat above 1-in-10-day | 4 | 5 | 9 | 9 | 9 | 9 | 9 |
| 2026-11-15 | model analysis (preliminary) | 0.0 | 0.0 | 33.4 | 10.8 | 29.7 | heat above 1-in-10-day | 3 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-11-16 | model analysis (preliminary) | 0.0 | 0.0 | 32.9 | 11.0 | 29.9 | heat above 1-in-10-day | 2 | 3 | 9 | 9 | 8 | 8 | 9 |
| 2026-11-17 | model analysis (preliminary) | 0.6 | 0.6 | 32.9 | 9.4 | 30.5 | rain heavy (above 1-in-10-day); heat above 1-in-10-day | 2 | 6 | 7 | 9 | 8 | 7 | 8 |
| 2026-11-18 | model analysis (preliminary) | 1.8 | 1.3 | 33.5 | 11.3 | 31.2 | rain heavy (above 1-in-10-day); heat above 1-in-10-day | 4 | 6 | 5 | 9 | 6 | 6 | 7 |
| 2026-11-19 | model analysis (preliminary) | 0.2 | 0.1 | 33.7 | 9.9 | 30.3 | heat above 1-in-10-day | 3 | 5 | 5 | 9 | 9 | 8 | 9 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*