# Site weather record · Jinja · November 2026

Site 0.4244, 33.2042. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 67.4 mm against a pro-rata normal of 88 mm (77 % of normal; full-month normal 202 mm, 1991-2020).
- Rain days (1 mm or more): 11 against a pro-rata normal of 11.4.
- Heavy rain days (above the site's 1-in-10-day amount, 14 mm): 1; exceptional (above 1-in-100-day, 28 mm): 0.
- Days with gusts above the 1-in-10-day value (8 m/s): 8; days hotter than the 1-in-10-day maximum (27.5 °C): 3.
- Working hours lost to weather (caution or stop): outdoor labour 1 h, concrete pour 15 h, asphalt & surfacing 91 h, crane lifts 0 h, work at height 36 h, painting & coatings 76 h, earthworks 48 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 2.7 | 0.8 | 28.2 | 5.9 | 28.6 | heat above 1-in-10-day | 7 | 6 | 0 | 8 | 5 | 3 | 1 |
| 2026-11-02 | ERA5 (final) | 1.6 | 0.6 | 27.5 | 6.0 | 27.4 | heat above 1-in-10-day | 8 | 8 | 0 | 8 | 6 | 3 | 7 |
| 2026-11-03 | ERA5 (final) | 5.1 | 2.2 | 26.0 | 7.2 | 27.9 |  | 8 | 6 | 0 | 8 | 3 | 0 | 4 |
| 2026-11-04 | ERA5 (final) | 0.7 | 0.4 | 27.8 | 8.5 | 26.9 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 8 | 5 | 8 | 6 | 1 | 7 |
| 2026-11-11 | ERA5 (final) | 15.2 | 4.6 | 26.8 | 7.0 | 26.3 | rain heavy (above 1-in-10-day) | 8 | 6 | 0 | 8 | 5 | 1 | 3 |
| 2026-11-12 | ERA5 (final) | 8.5 | 2.4 | 22.5 | 7.0 | 23.2 |  | 8 | 7 | 0 | 8 | 5 | 3 | 0 |
| 2026-11-13 | model analysis (preliminary) | 8.1 | 2.0 | 25.4 | 9.3 | 25.8 | gust above 1-in-10-day | 8 | 5 | 3 | 8 | 4 | 1 | 5 |
| 2026-11-14 | model analysis (preliminary) | 5.4 | 1.5 | 25.3 | 8.9 | 25.7 | gust above 1-in-10-day | 8 | 6 | 0 | 8 | 3 | 1 | 5 |
| 2026-11-15 | model analysis (preliminary) | 0.4 | 0.2 | 25.5 | 7.9 | 25.6 | gust above 1-in-10-day | 8 | 8 | 3 | 8 | 8 | 5 | 8 |
| 2026-11-16 | model analysis (preliminary) | 9.8 | 4.3 | 25.4 | 8.8 | 25.5 | gust above 1-in-10-day | 8 | 7 | 0 | 8 | 4 | 2 | 0 |
| 2026-11-17 | model analysis (preliminary) | 7.2 | 3.3 | 25.2 | 8.3 | 25.3 | gust above 1-in-10-day | 8 | 6 | 0 | 8 | 5 | 1 | 0 |
| 2026-11-18 | model analysis (preliminary) | 1.5 | 0.8 | 25.7 | 7.9 | 25.2 | gust above 1-in-10-day | 8 | 8 | 0 | 8 | 8 | 4 | 8 |
| 2026-11-19 | model analysis (preliminary) | 1.2 | 0.3 | 26.4 | 9.5 | 25.9 | gust above 1-in-10-day | 8 | 8 | 2 | 8 | 6 | 3 | 8 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*