# Site weather record · Kuwait City · March 2026

Site 29.3759, 47.9774. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 93.2 mm against a pro-rata normal of 16 mm (575 % of normal; full-month normal 16 mm, 1991-2020).
- Rain days (1 mm or more): 10 against a pro-rata normal of 2.7.
- Heavy rain days (above the site's 1-in-10-day amount, 1 mm): 10; exceptional (above 1-in-100-day, 11 mm): 1.
- Days with gusts above the 1-in-10-day value (14 m/s): 3; days hotter than the 1-in-10-day maximum (27.6 °C): 0.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 103 h, asphalt & surfacing 86 h, crane lifts 1 h, work at height 53 h, painting & coatings 95 h, earthworks 61 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-03-01 | ERA5 (final) | 0.0 | 0.0 | 22.1 | 12.5 | 16.7 |  | 9 | 1 | 2 | 9 | 2 | 9 | 9 |
| 2026-03-02 | ERA5 (final) | 0.0 | 0.0 | 21.8 | 12.7 | 16.2 |  | 9 | 0 | 0 | 9 | 2 | 9 | 9 |
| 2026-03-03 | ERA5 (final) | 0.0 | 0.0 | 19.9 | 11.1 | 15.0 |  | 9 | 2 | 9 | 9 | 8 | 9 | 9 |
| 2026-03-04 | ERA5 (final) | 0.0 | 0.0 | 20.0 | 9.8 | 14.5 |  | 9 | 2 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-05 | ERA5 (final) | 0.0 | 0.0 | 22.6 | 5.3 | 19.4 |  | 9 | 9 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-06 | ERA5 (final) | 0.0 | 0.0 | 20.8 | 6.6 | 15.9 |  | 9 | 6 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-07 | ERA5 (final) | 0.8 | 0.3 | 20.7 | 7.8 | 17.3 | rain heavy (above 1-in-10-day) | 9 | 7 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-08 | ERA5 (final) | 1.4 | 0.3 | 22.6 | 11.2 | 19.9 | rain heavy (above 1-in-10-day) | 9 | 2 | 1 | 9 | 6 | 6 | 8 |
| 2026-03-09 | ERA5 (final) | 0.0 | 0.0 | 20.2 | 11.6 | 15.3 |  | 9 | 2 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-10 | ERA5 (final) | 0.0 | 0.0 | 21.3 | 7.9 | 17.7 |  | 9 | 5 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-11 | ERA5 (final) | 0.0 | 0.0 | 23.3 | 8.4 | 18.4 |  | 9 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-12 | ERA5 (final) | 7.3 | 1.3 | 20.6 | 8.2 | 18.7 | rain heavy (above 1-in-10-day) | 9 | 6 | 0 | 9 | 4 | 4 | 5 |
| 2026-03-13 | ERA5 (final) | 6.5 | 1.7 | 20.7 | 7.1 | 20.5 | rain heavy (above 1-in-10-day) | 9 | 8 | 0 | 9 | 4 | 0 | 0 |
| 2026-03-14 | ERA5 (final) | 0.0 | 0.0 | 23.1 | 4.7 | 23.9 |  | 9 | 9 | 9 | 9 | 9 | 4 | 9 |
| 2026-03-15 | ERA5 (final) | 0.4 | 0.2 | 21.3 | 10.7 | 20.5 |  | 9 | 9 | 7 | 9 | 9 | 1 | 9 |
| 2026-03-16 | ERA5 (final) | 0.6 | 0.3 | 23.3 | 9.3 | 21.6 |  | 9 | 9 | 3 | 9 | 8 | 6 | 8 |
| 2026-03-17 | ERA5 (final) | 0.0 | 0.0 | 23.3 | 11.3 | 19.5 |  | 9 | 4 | 9 | 9 | 9 | 8 | 9 |
| 2026-03-18 | ERA5 (final) | 0.0 | 0.0 | 24.0 | 9.1 | 19.8 |  | 9 | 4 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-19 | ERA5 (final) | 5.2 | 1.7 | 22.6 | 14.8 | 19.3 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 9 | 5 | 6 | 9 | 7 | 7 | 9 |
| 2026-03-20 | ERA5 (final) | 2.4 | 0.9 | 24.1 | 13.0 | 23.6 | rain heavy (above 1-in-10-day) | 9 | 9 | 8 | 9 | 9 | 5 | 0 |
| 2026-03-21 | ERA5 (final) | 0.0 | 0.0 | 23.1 | 6.0 | 22.2 |  | 9 | 9 | 9 | 9 | 9 | 7 | 9 |
| 2026-03-22 | ERA5 (final) | 5.8 | 1.9 | 21.8 | 14.2 | 21.7 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 9 | 6 | 2 | 8 | 5 | 0 | 0 |
| 2026-03-23 | ERA5 (final) | 7.2 | 2.4 | 22.9 | 8.7 | 22.3 | rain heavy (above 1-in-10-day) | 9 | 8 | 4 | 9 | 6 | 0 | 8 |
| 2026-03-24 | ERA5 (final) | 3.4 | 2.4 | 22.1 | 9.5 | 21.6 | rain heavy (above 1-in-10-day) | 9 | 9 | 6 | 9 | 8 | 0 | 1 |
| 2026-03-25 | ERA5 (final) | 11.2 | 5.6 | 22.5 | 12.2 | 21.9 | rain heavy (above 1-in-10-day) | 9 | 6 | 1 | 9 | 2 | 0 | 4 |
| 2026-03-26 | ERA5 (final) | 41.0 | 11.2 | 22.3 | 15.0 | 21.8 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 9 | 4 | 0 | 9 | 2 | 0 | 0 |
| 2026-03-27 | ERA5 (final) | 0.0 | 0.0 | 21.3 | 9.7 | 18.4 |  | 9 | 5 | 9 | 9 | 9 | 8 | 4 |
| 2026-03-28 | ERA5 (final) | 0.0 | 0.0 | 23.6 | 6.9 | 20.4 |  | 9 | 6 | 9 | 9 | 9 | 7 | 9 |
| 2026-03-29 | ERA5 (final) | 0.0 | 0.0 | 23.4 | 5.6 | 22.8 |  | 9 | 9 | 9 | 9 | 9 | 7 | 9 |
| 2026-03-30 | ERA5 (final) | 0.0 | 0.0 | 23.1 | 11.6 | 21.1 |  | 9 | 3 | 9 | 9 | 9 | 8 | 9 |
| 2026-03-31 | ERA5 (final) | 0.0 | 0.0 | 24.9 | 10.9 | 24.0 |  | 9 | 9 | 9 | 9 | 9 | 7 | 9 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*