# Site weather record · Lagos · June 2026

Site 6.5244, 3.3792. 30 of 30 days recorded, 30 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 518.5 mm against a pro-rata normal of 293 mm (177 % of normal; full-month normal 293 mm, 1991-2020).
- Rain days (1 mm or more): 28 against a pro-rata normal of 28.1.
- Heavy rain days (above the site's 1-in-10-day amount, 18 mm): 3; exceptional (above 1-in-100-day, 53 mm): 3.
- Days with gusts above the 1-in-10-day value (10 m/s): 0; days hotter than the 1-in-10-day maximum (29.1 °C): 11.
- Working hours lost to weather (caution or stop): outdoor labour 90 h, concrete pour 81 h, asphalt & surfacing 232 h, crane lifts 0 h, work at height 147 h, painting & coatings 234 h, earthworks 186 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-06-01 | ERA5 (final) | 5.0 | 0.9 | 29.8 | 7.1 | 30.5 | heat above 1-in-10-day | 1 | 6 | 0 | 8 | 4 | 0 | 4 |
| 2026-06-02 | ERA5 (final) | 6.1 | 2.4 | 30.7 | 7.7 | 30.6 | heat above 1-in-10-day | 1 | 7 | 0 | 8 | 4 | 0 | 7 |
| 2026-06-03 | ERA5 (final) | 20.3 | 7.5 | 28.9 | 9.5 | 30.0 | rain heavy (above 1-in-10-day) | 5 | 5 | 0 | 8 | 4 | 0 | 1 |
| 2026-06-04 | ERA5 (final) | 8.4 | 3.1 | 29.7 | 7.7 | 29.6 | heat above 1-in-10-day | 3 | 8 | 0 | 8 | 6 | 0 | 0 |
| 2026-06-05 | ERA5 (final) | 19.7 | 5.1 | 29.4 | 8.5 | 29.5 | rain heavy (above 1-in-10-day); heat above 1-in-10-day | 2 | 5 | 0 | 8 | 3 | 0 | 5 |
| 2026-06-06 | ERA5 (final) | 11.9 | 1.6 | 27.9 | 7.4 | 27.7 |  | 8 | 7 | 0 | 8 | 3 | 0 | 0 |
| 2026-06-07 | ERA5 (final) | 13.2 | 1.8 | 29.7 | 6.6 | 30.0 | heat above 1-in-10-day | 4 | 5 | 0 | 8 | 4 | 0 | 0 |
| 2026-06-08 | ERA5 (final) | 13.1 | 5.7 | 29.1 | 7.0 | 29.2 | heat above 1-in-10-day | 3 | 6 | 0 | 8 | 4 | 0 | 4 |
| 2026-06-09 | ERA5 (final) | 13.1 | 1.9 | 28.7 | 8.0 | 28.8 |  | 4 | 5 | 0 | 8 | 0 | 0 | 0 |
| 2026-06-10 | ERA5 (final) | 6.2 | 1.5 | 29.3 | 6.1 | 29.3 | heat above 1-in-10-day | 2 | 7 | 0 | 8 | 4 | 0 | 0 |
| 2026-06-11 | ERA5 (final) | 7.5 | 2.0 | 30.2 | 6.3 | 30.5 | heat above 1-in-10-day | 3 | 8 | 2 | 8 | 8 | 4 | 0 |
| 2026-06-12 | ERA5 (final) | 10.2 | 3.1 | 28.6 | 7.0 | 30.0 |  | 4 | 2 | 0 | 8 | 0 | 0 | 1 |
| 2026-06-13 | ERA5 (final) | 0.1 | 0.1 | 29.3 | 5.2 | 29.2 | heat above 1-in-10-day | 4 | 8 | 4 | 8 | 8 | 2 | 3 |
| 2026-06-14 | ERA5 (final) | 9.0 | 2.2 | 27.8 | 5.5 | 27.9 |  | 8 | 3 | 0 | 8 | 0 | 0 | 1 |
| 2026-06-15 | ERA5 (final) | 0.7 | 0.2 | 28.6 | 6.0 | 28.3 |  | 5 | 8 | 1 | 8 | 8 | 0 | 5 |
| 2026-06-16 | ERA5 (final) | 7.0 | 2.9 | 29.4 | 7.2 | 29.8 | heat above 1-in-10-day | 2 | 5 | 0 | 8 | 4 | 0 | 5 |
| 2026-06-17 | ERA5 (final) | 9.2 | 1.8 | 27.5 | 6.4 | 27.7 |  | 8 | 2 | 0 | 8 | 0 | 0 | 0 |
| 2026-06-18 | ERA5 (final) | 6.5 | 2.1 | 30.0 | 5.2 | 30.1 | heat above 1-in-10-day | 2 | 8 | 0 | 8 | 3 | 0 | 1 |
| 2026-06-19 | ERA5 (final) | 4.1 | 1.0 | 27.2 | 9.0 | 27.2 |  | 8 | 7 | 0 | 8 | 4 | 0 | 7 |
| 2026-06-20 | ERA5 (final) | 11.5 | 2.3 | 28.2 | 6.7 | 28.8 |  | 6 | 5 | 0 | 8 | 3 | 0 | 0 |
| 2026-06-21 | ERA5 (final) | 78.1 | 16.5 | 27.5 | 8.3 | 27.5 | rain exceptional (above 1-in-100-day) | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-06-22 | ERA5 (final) | 17.7 | 6.1 | 27.3 | 6.1 | 28.6 |  | 7 | 4 | 0 | 8 | 2 | 0 | 0 |
| 2026-06-23 | ERA5 (final) | 1.5 | 0.2 | 28.5 | 7.1 | 28.4 |  | 3 | 8 | 0 | 8 | 4 | 0 | 2 |
| 2026-06-24 | ERA5 (final) | 9.6 | 4.1 | 28.5 | 6.9 | 28.3 |  | 7 | 4 | 0 | 8 | 1 | 0 | 2 |
| 2026-06-25 | ERA5 (final) | 2.9 | 0.7 | 27.6 | 7.3 | 28.2 |  | 6 | 6 | 1 | 8 | 2 | 0 | 0 |
| 2026-06-26 | ERA5 (final) | 4.9 | 2.0 | 28.7 | 8.0 | 28.8 |  | 5 | 8 | 0 | 8 | 3 | 0 | 6 |
| 2026-06-27 | ERA5 (final) | 8.2 | 3.0 | 28.5 | 7.7 | 28.6 |  | 7 | 6 | 0 | 8 | 3 | 0 | 0 |
| 2026-06-28 | ERA5 (final) | 20.6 | 6.9 | 27.4 | 7.3 | 27.6 | rain heavy (above 1-in-10-day) | 8 | 2 | 0 | 8 | 2 | 0 | 0 |
| 2026-06-29 | ERA5 (final) | 78.2 | 17.0 | 28.3 | 9.1 | 27.9 | rain exceptional (above 1-in-100-day) | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-06-30 | ERA5 (final) | 114.0 | 18.1 | 26.3 | 6.1 | 25.2 | rain exceptional (above 1-in-100-day) | 8 | 0 | 0 | 8 | 0 | 0 | 0 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*