# Site weather record · Lagos · September 2026

Site 6.5244, 3.3792. 30 of 30 days recorded, 30 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 515.7 mm against a pro-rata normal of 192 mm (269 % of normal; full-month normal 192 mm, 1991-2020).
- Rain days (1 mm or more): 26 against a pro-rata normal of 25.4.
- Heavy rain days (above the site's 1-in-10-day amount, 13 mm): 4; exceptional (above 1-in-100-day, 47 mm): 2.
- Days with gusts above the 1-in-10-day value (10 m/s): 4; days hotter than the 1-in-10-day maximum (28.1 °C): 16.
- Working hours lost to weather (caution or stop): outdoor labour 30 h, concrete pour 74 h, asphalt & surfacing 232 h, crane lifts 0 h, work at height 127 h, painting & coatings 240 h, earthworks 155 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-09-01 | ERA5 (final) | 0.7 | 0.2 | 29.0 | 8.7 | 29.0 | heat above 1-in-10-day | 3 | 8 | 2 | 8 | 6 | 0 | 8 |
| 2026-09-02 | ERA5 (final) | 0.7 | 0.2 | 27.6 | 8.4 | 27.8 |  | 8 | 8 | 4 | 8 | 7 | 0 | 8 |
| 2026-09-03 | ERA5 (final) | 1.0 | 0.1 | 28.0 | 7.7 | 28.1 |  | 7 | 8 | 0 | 8 | 8 | 0 | 8 |
| 2026-09-04 | ERA5 (final) | 3.0 | 0.6 | 28.2 | 8.6 | 28.4 | heat above 1-in-10-day | 6 | 6 | 0 | 8 | 5 | 0 | 5 |
| 2026-09-05 | ERA5 (final) | 116.7 | 15.0 | 27.3 | 8.7 | 25.8 | rain exceptional (above 1-in-100-day) | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-09-06 | ERA5 (final) | 3.5 | 1.6 | 27.8 | 9.5 | 27.5 |  | 8 | 6 | 0 | 8 | 5 | 0 | 0 |
| 2026-09-07 | ERA5 (final) | 11.1 | 3.4 | 27.3 | 5.3 | 27.7 |  | 8 | 4 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-08 | ERA5 (final) | 0.6 | 0.2 | 28.4 | 7.1 | 28.4 | heat above 1-in-10-day | 5 | 8 | 0 | 8 | 8 | 0 | 4 |
| 2026-09-09 | ERA5 (final) | 4.9 | 3.4 | 27.4 | 8.9 | 27.8 |  | 8 | 7 | 0 | 8 | 5 | 0 | 7 |
| 2026-09-10 | ERA5 (final) | 6.6 | 1.2 | 28.4 | 9.4 | 27.8 | heat above 1-in-10-day | 8 | 6 | 0 | 8 | 2 | 0 | 0 |
| 2026-09-11 | ERA5 (final) | 12.4 | 4.0 | 27.1 | 8.6 | 27.1 |  | 8 | 3 | 0 | 8 | 2 | 0 | 0 |
| 2026-09-12 | ERA5 (final) | 6.4 | 3.0 | 28.2 | 8.3 | 28.6 | heat above 1-in-10-day | 7 | 6 | 0 | 8 | 2 | 0 | 1 |
| 2026-09-13 | ERA5 (final) | 3.5 | 2.5 | 28.1 | 7.6 | 28.5 | heat above 1-in-10-day | 5 | 7 | 1 | 8 | 7 | 0 | 5 |
| 2026-09-14 | ERA5 (final) | 44.0 | 7.7 | 27.4 | 7.1 | 27.8 | rain heavy (above 1-in-10-day) | 8 | 5 | 0 | 8 | 2 | 0 | 0 |
| 2026-09-15 | ERA5 (final) | 2.8 | 1.0 | 28.8 | 10.2 | 28.4 | gust above 1-in-10-day; heat above 1-in-10-day | 3 | 8 | 0 | 8 | 7 | 0 | 0 |
| 2026-09-16 | ERA5 (final) | 2.2 | 0.4 | 28.5 | 9.9 | 27.9 | heat above 1-in-10-day | 8 | 8 | 0 | 8 | 7 | 0 | 7 |
| 2026-09-17 | ERA5 (final) | 3.8 | 1.8 | 28.3 | 9.6 | 27.7 | heat above 1-in-10-day | 8 | 7 | 0 | 8 | 5 | 0 | 6 |
| 2026-09-18 | ERA5 (final) | 7.6 | 2.6 | 28.5 | 10.0 | 28.1 | gust above 1-in-10-day; heat above 1-in-10-day | 6 | 7 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-19 | ERA5 (final) | 7.4 | 1.6 | 28.2 | 9.1 | 28.2 | heat above 1-in-10-day | 6 | 4 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-20 | ERA5 (final) | 12.2 | 1.8 | 27.6 | 8.4 | 27.2 |  | 8 | 3 | 0 | 8 | 3 | 0 | 0 |
| 2026-09-21 | ERA5 (final) | 10.5 | 1.0 | 27.5 | 8.7 | 27.3 |  | 8 | 4 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-22 | ERA5 (final) | 44.0 | 7.3 | 26.8 | 7.2 | 26.0 | rain heavy (above 1-in-10-day) | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-23 | ERA5 (final) | 9.3 | 0.9 | 27.1 | 6.8 | 26.9 |  | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-24 | ERA5 (final) | 7.3 | 3.1 | 27.8 | 7.0 | 28.7 |  | 6 | 6 | 1 | 8 | 3 | 0 | 2 |
| 2026-09-25 | ERA5 (final) | 1.7 | 0.3 | 28.3 | 8.9 | 28.2 | heat above 1-in-10-day | 7 | 8 | 0 | 8 | 3 | 0 | 3 |
| 2026-09-26 | ERA5 (final) | 1.5 | 0.2 | 28.6 | 9.4 | 27.9 | heat above 1-in-10-day | 8 | 8 | 0 | 8 | 6 | 0 | 8 |
| 2026-09-27 | ERA5 (final) | 21.9 | 5.6 | 28.2 | 10.9 | 27.4 | rain heavy (above 1-in-10-day); gust above 1-in-10-day; heat above 1-in-10-day | 8 | 7 | 0 | 8 | 5 | 0 | 7 |
| 2026-09-28 | ERA5 (final) | 145.9 | 12.9 | 26.8 | 11.0 | 25.5 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-09-29 | ERA5 (final) | 21.9 | 3.5 | 28.2 | 9.0 | 27.4 | rain heavy (above 1-in-10-day); heat above 1-in-10-day | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-09-30 | ERA5 (final) | 0.6 | 0.1 | 28.9 | 8.4 | 28.3 | heat above 1-in-10-day | 5 | 8 | 0 | 8 | 8 | 0 | 6 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*