# Site weather record · Lagos · November 2026

Site 6.5244, 3.3792. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 36.1 mm against a pro-rata normal of 34 mm (106 % of normal; full-month normal 79 mm, 1991-2020).
- Rain days (1 mm or more): 9 against a pro-rata normal of 8.4.
- Heavy rain days (above the site's 1-in-10-day amount, 7 mm): 2; exceptional (above 1-in-100-day, 15 mm): 0.
- Days with gusts above the 1-in-10-day value (8 m/s): 5; days hotter than the 1-in-10-day maximum (30.3 °C): 8.
- Working hours lost to weather (caution or stop): outdoor labour 84 h, concrete pour 10 h, asphalt & surfacing 75 h, crane lifts 0 h, work at height 30 h, painting & coatings 80 h, earthworks 23 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 0.3 | 0.1 | 30.2 | 6.9 | 30.0 |  | 1 | 8 | 5 | 8 | 8 | 2 | 8 |
| 2026-11-02 | ERA5 (final) | 4.4 | 2.1 | 31.0 | 5.8 | 31.4 | heat above 1-in-10-day | 1 | 7 | 0 | 8 | 5 | 0 | 7 |
| 2026-11-03 | ERA5 (final) | 10.5 | 2.6 | 29.8 | 6.6 | 28.8 | rain heavy (above 1-in-10-day) | 5 | 4 | 0 | 8 | 2 | 0 | 0 |
| 2026-11-04 | ERA5 (final) | 2.4 | 0.9 | 30.1 | 7.0 | 30.4 |  | 1 | 7 | 0 | 8 | 4 | 0 | 4 |
| 2026-11-05 | ERA5 (final) | 1.2 | 0.3 | 30.3 | 8.5 | 30.2 | gust above 1-in-10-day; heat above 1-in-10-day | 2 | 8 | 1 | 8 | 6 | 0 | 7 |
| 2026-11-12 | ERA5 (final) | 7.3 | 2.7 | 29.2 | 6.5 | 29.6 | rain heavy (above 1-in-10-day) | 3 | 7 | 0 | 8 | 5 | 0 | 6 |
| 2026-11-13 | model analysis (preliminary) | 0.5 | 0.2 | 29.9 | 8.6 | 29.5 | gust above 1-in-10-day | 1 | 8 | 5 | 8 | 8 | 5 | 8 |
| 2026-11-14 | model analysis (preliminary) | 0.8 | 0.2 | 30.3 | 7.5 | 29.8 | heat above 1-in-10-day | 1 | 8 | 0 | 8 | 6 | 4 | 8 |
| 2026-11-15 | model analysis (preliminary) | 1.4 | 1.1 | 30.9 | 7.7 | 31.4 | heat above 1-in-10-day | 1 | 7 | 4 | 8 | 7 | 3 | 7 |
| 2026-11-16 | model analysis (preliminary) | 0.0 | 0.0 | 31.6 | 7.8 | 31.5 | heat above 1-in-10-day | 1 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-11-17 | model analysis (preliminary) | 2.8 | 0.8 | 31.5 | 9.1 | 31.0 | gust above 1-in-10-day; heat above 1-in-10-day | 1 | 6 | 1 | 8 | 5 | 1 | 6 |
| 2026-11-18 | model analysis (preliminary) | 2.1 | 0.9 | 31.4 | 8.2 | 31.6 | gust above 1-in-10-day; heat above 1-in-10-day | 1 | 8 | 5 | 8 | 5 | 2 | 5 |
| 2026-11-19 | model analysis (preliminary) | 2.4 | 1.0 | 31.8 | 8.1 | 31.5 | gust above 1-in-10-day; heat above 1-in-10-day | 1 | 8 | 0 | 8 | 5 | 2 | 7 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*
