# Site weather record · Lusaka · November 2026

Site -15.3875, 28.3228. 13 of 30 days recorded, 6 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 24.1 mm against a pro-rata normal of 43 mm (56 % of normal; full-month normal 98 mm, 1991-2020).
- Rain days (1 mm or more): 5 against a pro-rata normal of 6.2.
- Heavy rain days (above the site's 1-in-10-day amount, 10 mm): 1; exceptional (above 1-in-100-day, 25 mm): 0.
- Days with gusts above the 1-in-10-day value (14 m/s): 0; days hotter than the 1-in-10-day maximum (33.3 °C): 6.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 77 h, asphalt & surfacing 29 h, crane lifts 2 h, work at height 29 h, painting & coatings 15 h, earthworks 12 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-11-01 | ERA5 (final) | 0.0 | 0.0 | 34.2 | 8.5 | 25.5 | heat above 1-in-10-day | 8 | 0 | 8 | 8 | 8 | 8 | 8 |
| 2026-11-02 | ERA5 (final) | 0.0 | 0.0 | 35.2 | 10.2 | 26.2 | heat above 1-in-10-day | 8 | 0 | 8 | 8 | 8 | 8 | 8 |
| 2026-11-03 | ERA5 (final) | 0.0 | 0.0 | 35.2 | 12.0 | 26.1 | heat above 1-in-10-day | 8 | 0 | 8 | 8 | 6 | 8 | 8 |
| 2026-11-04 | ERA5 (final) | 0.0 | 0.0 | 35.7 | 11.4 | 26.8 | heat above 1-in-10-day | 8 | 0 | 8 | 8 | 6 | 8 | 8 |
| 2026-11-05 | ERA5 (final) | 0.0 | 0.0 | 34.7 | 11.9 | 26.5 | heat above 1-in-10-day | 8 | 0 | 8 | 8 | 5 | 8 | 8 |
| 2026-11-12 | ERA5 (final) | 0.0 | 0.0 | 34.7 | 7.7 | 27.4 | heat above 1-in-10-day | 8 | 2 | 8 | 8 | 8 | 8 | 8 |
| 2026-11-13 | model analysis (preliminary) | 0.2 | 0.1 | 33.3 | 9.2 | 26.6 |  | 8 | 1 | 5 | 8 | 8 | 8 | 8 |
| 2026-11-14 | model analysis (preliminary) | 0.5 | 0.4 | 32.8 | 11.9 | 27.4 |  | 8 | 2 | 8 | 8 | 5 | 8 | 8 |
| 2026-11-15 | model analysis (preliminary) | 11.0 | 4.1 | 30.6 | 10.2 | 26.7 | rain heavy (above 1-in-10-day) | 8 | 6 | 5 | 8 | 5 | 5 | 5 |
| 2026-11-16 | model analysis (preliminary) | 1.6 | 1.1 | 29.5 | 8.8 | 26.8 |  | 8 | 6 | 4 | 8 | 6 | 6 | 7 |
| 2026-11-17 | model analysis (preliminary) | 3.8 | 2.3 | 30.3 | 11.0 | 25.8 |  | 8 | 0 | 2 | 8 | 5 | 5 | 6 |
| 2026-11-18 | model analysis (preliminary) | 2.6 | 0.9 | 27.5 | 13.7 | 24.4 |  | 8 | 5 | 2 | 6 | 2 | 7 | 7 |
| 2026-11-19 | model analysis (preliminary) | 4.4 | 1.4 | 26.3 | 8.3 | 25.1 |  | 8 | 5 | 1 | 8 | 3 | 2 | 3 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*