Site weather, Lusaka: Friday 20 November. Storms likely from 16:00: finish lifts, roof and asphalt work before then. • Concrete pour: go 08-13 h only. • Asphalt & surfacing: go 08-13 h only. • Crane lifts: go 08-13 h, 14-15 h only. • Work at height: go 08-13 h only. • Painting & coatings: go 08-13 h only. • Earthworks: go 08-13 h, 14-15 h only. • No limits: Outdoor labour. Hour-by-hour for seven trades, the week ahead and the monthly record: gavacharles.github.io/kampala-heat-atlas/site-weather/lusaka Screening guidance from a forecast; your contract, crane limits and H&S plan come first. #Lusaka #Construction #SiteSafety #HeatStress #Zambia #Weather