# Site weather record · Manama · March 2026

Site 26.2285, 50.5860. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 87.1 mm against a pro-rata normal of 10 mm (857 % of normal; full-month normal 10 mm, 1991-2020).
- Rain days (1 mm or more): 11 against a pro-rata normal of 1.9.
- Heavy rain days (above the site's 1-in-10-day amount, 0 mm): 9; exceptional (above 1-in-100-day, 7 mm): 4.
- Days with gusts above the 1-in-10-day value (14 m/s): 3; days hotter than the 1-in-10-day maximum (23.9 °C): 3.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 35 h, asphalt & surfacing 85 h, crane lifts 17 h, work at height 49 h, painting & coatings 178 h, earthworks 56 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-03-01 | ERA5 (final) | 0.0 | 0.0 | 20.6 | 10.8 | 19.8 |  | 9 | 9 | 7 | 9 | 9 | 3 | 9 |
| 2026-03-02 | ERA5 (final) | 0.1 | 0.1 | 20.3 | 11.8 | 19.3 |  | 9 | 8 | 2 | 9 | 7 | 7 | 9 |
| 2026-03-03 | ERA5 (final) | 6.1 | 0.9 | 20.5 | 14.5 | 18.1 | rain heavy (above 1-in-10-day); gust above 1-in-10-day | 9 | 1 | 0 | 0 | 0 | 4 | 5 |
| 2026-03-04 | ERA5 (final) | 15.6 | 2.9 | 19.3 | 12.2 | 18.0 | rain exceptional (above 1-in-100-day) | 9 | 0 | 0 | 9 | 0 | 4 | 0 |
| 2026-03-05 | ERA5 (final) | 0.0 | 0.0 | 19.3 | 10.3 | 16.9 |  | 9 | 3 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-06 | ERA5 (final) | 0.0 | 0.0 | 19.5 | 11.0 | 18.5 |  | 9 | 7 | 6 | 9 | 8 | 9 | 9 |
| 2026-03-07 | ERA5 (final) | 0.0 | 0.0 | 20.3 | 7.8 | 20.9 |  | 9 | 9 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-08 | ERA5 (final) | 0.5 | 0.2 | 20.9 | 8.7 | 20.8 | rain heavy (above 1-in-10-day) | 9 | 9 | 4 | 9 | 8 | 5 | 9 |
| 2026-03-09 | ERA5 (final) | 0.4 | 0.2 | 20.7 | 8.7 | 21.6 | rain heavy (above 1-in-10-day) | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-10 | ERA5 (final) | 3.8 | 0.3 | 19.4 | 10.3 | 19.2 | rain heavy (above 1-in-10-day) | 9 | 9 | 0 | 9 | 4 | 1 | 8 |
| 2026-03-11 | ERA5 (final) | 1.4 | 0.6 | 20.3 | 7.8 | 20.4 | rain heavy (above 1-in-10-day) | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-12 | ERA5 (final) | 0.1 | 0.1 | 20.8 | 9.3 | 21.6 |  | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-13 | ERA5 (final) | 0.0 | 0.0 | 20.9 | 7.1 | 22.6 |  | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-14 | ERA5 (final) | 0.0 | 0.0 | 21.2 | 8.2 | 22.0 |  | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-15 | ERA5 (final) | 0.0 | 0.0 | 23.7 | 9.9 | 24.3 |  | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-16 | ERA5 (final) | 0.1 | 0.1 | 24.0 | 9.4 | 23.9 | heat above 1-in-10-day | 9 | 9 | 7 | 9 | 9 | 0 | 9 |
| 2026-03-17 | ERA5 (final) | 0.0 | 0.0 | 22.5 | 12.7 | 21.7 |  | 9 | 9 | 4 | 9 | 5 | 0 | 9 |
| 2026-03-18 | ERA5 (final) | 0.0 | 0.0 | 21.7 | 10.9 | 20.6 |  | 9 | 9 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-19 | ERA5 (final) | 0.2 | 0.2 | 21.6 | 7.9 | 20.7 |  | 9 | 9 | 9 | 9 | 9 | 6 | 9 |
| 2026-03-20 | ERA5 (final) | 2.7 | 0.9 | 22.6 | 9.4 | 22.9 | rain heavy (above 1-in-10-day) | 9 | 6 | 3 | 9 | 5 | 0 | 5 |
| 2026-03-21 | ERA5 (final) | 0.0 | 0.0 | 22.3 | 8.1 | 23.3 |  | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-22 | ERA5 (final) | 0.0 | 0.0 | 23.6 | 11.2 | 24.3 |  | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-23 | ERA5 (final) | 1.3 | 1.3 | 23.4 | 11.9 | 23.6 | rain heavy (above 1-in-10-day) | 9 | 9 | 9 | 9 | 9 | 0 | 9 |
| 2026-03-24 | ERA5 (final) | 16.7 | 8.6 | 22.2 | 9.7 | 23.4 | rain exceptional (above 1-in-100-day) | 9 | 9 | 4 | 9 | 9 | 0 | 0 |
| 2026-03-25 | ERA5 (final) | 17.5 | 4.9 | 23.0 | 14.5 | 23.7 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day | 9 | 8 | 2 | 9 | 7 | 0 | 0 |
| 2026-03-26 | ERA5 (final) | 17.2 | 6.6 | 24.3 | 18.9 | 24.0 | rain exceptional (above 1-in-100-day); gust above 1-in-10-day; heat above 1-in-10-day | 9 | 8 | 0 | 2 | 1 | 0 | 0 |
| 2026-03-27 | ERA5 (final) | 1.0 | 0.4 | 22.3 | 11.3 | 20.9 | rain heavy (above 1-in-10-day) | 9 | 9 | 9 | 9 | 9 | 9 | 0 |
| 2026-03-28 | ERA5 (final) | 0.0 | 0.0 | 22.8 | 7.7 | 19.9 |  | 9 | 5 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-29 | ERA5 (final) | 0.0 | 0.0 | 24.0 | 7.8 | 23.0 | heat above 1-in-10-day | 9 | 9 | 9 | 9 | 9 | 8 | 9 |
| 2026-03-30 | ERA5 (final) | 0.0 | 0.0 | 22.9 | 10.6 | 21.8 |  | 9 | 9 | 9 | 9 | 9 | 9 | 9 |
| 2026-03-31 | ERA5 (final) | 2.4 | 0.5 | 22.3 | 13.6 | 21.3 | rain heavy (above 1-in-10-day) | 9 | 9 | 2 | 8 | 5 | 0 | 7 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*