# Site weather record · Mbale · March 2026

Site 1.0821, 34.1750. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 1118.7 mm against a pro-rata normal of 676 mm (165 % of normal; full-month normal 676 mm, 1991-2020).
- Rain days (1 mm or more): 31 against a pro-rata normal of 28.7.
- Heavy rain days (above the site's 1-in-10-day amount, 46 mm): 5; exceptional (above 1-in-100-day, 105 mm): 2.
- Days with gusts above the 1-in-10-day value (11 m/s): 0; days hotter than the 1-in-10-day maximum (30.5 °C): 0.
- Working hours lost to weather (caution or stop): outdoor labour 2 h, concrete pour 163 h, asphalt & surfacing 238 h, crane lifts 0 h, work at height 199 h, painting & coatings 228 h, earthworks 244 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-03-01 | ERA5 (final) | 87.6 | 9.0 | 24.2 | 5.7 | 24.1 | rain heavy (above 1-in-10-day) | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-02 | ERA5 (final) | 32.0 | 2.5 | 25.1 | 8.3 | 24.9 |  | 8 | 3 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-03 | ERA5 (final) | 27.0 | 3.0 | 24.7 | 6.3 | 24.5 |  | 8 | 1 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-04 | ERA5 (final) | 24.8 | 3.4 | 24.0 | 6.9 | 25.1 |  | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-05 | ERA5 (final) | 36.3 | 7.2 | 25.0 | 8.1 | 25.4 |  | 8 | 1 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-06 | ERA5 (final) | 54.2 | 4.8 | 24.8 | 5.7 | 24.9 | rain heavy (above 1-in-10-day) | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-03-07 | ERA5 (final) | 30.0 | 4.7 | 27.0 | 6.8 | 26.2 |  | 8 | 5 | 0 | 8 | 2 | 0 | 0 |
| 2026-03-08 | ERA5 (final) | 11.2 | 3.5 | 28.2 | 7.5 | 27.9 |  | 8 | 3 | 0 | 8 | 1 | 1 | 0 |
| 2026-03-09 | ERA5 (final) | 13.9 | 1.9 | 28.8 | 6.8 | 28.3 |  | 7 | 4 | 0 | 8 | 2 | 2 | 0 |
| 2026-03-10 | ERA5 (final) | 38.1 | 5.2 | 26.6 | 7.5 | 28.3 |  | 8 | 1 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-11 | ERA5 (final) | 35.1 | 4.6 | 26.1 | 7.1 | 26.7 |  | 8 | 2 | 0 | 8 | 2 | 0 | 0 |
| 2026-03-12 | ERA5 (final) | 21.1 | 3.2 | 27.7 | 7.5 | 27.5 |  | 8 | 4 | 0 | 8 | 3 | 0 | 0 |
| 2026-03-13 | ERA5 (final) | 2.5 | 1.8 | 28.5 | 7.7 | 27.8 |  | 8 | 8 | 2 | 8 | 5 | 2 | 0 |
| 2026-03-14 | ERA5 (final) | 10.1 | 2.9 | 28.1 | 6.5 | 28.0 |  | 8 | 6 | 3 | 8 | 4 | 2 | 4 |
| 2026-03-15 | ERA5 (final) | 10.5 | 2.8 | 27.8 | 8.0 | 28.0 |  | 7 | 5 | 0 | 8 | 4 | 3 | 0 |
| 2026-03-16 | ERA5 (final) | 13.9 | 4.1 | 27.9 | 8.9 | 27.3 |  | 8 | 3 | 0 | 8 | 2 | 0 | 0 |
| 2026-03-17 | ERA5 (final) | 2.6 | 0.7 | 29.0 | 7.6 | 27.4 |  | 8 | 6 | 5 | 8 | 6 | 5 | 0 |
| 2026-03-18 | ERA5 (final) | 23.0 | 3.5 | 25.9 | 7.2 | 26.6 |  | 8 | 2 | 0 | 8 | 1 | 0 | 0 |
| 2026-03-19 | ERA5 (final) | 143.7 | 16.8 | 25.6 | 6.4 | 26.7 | rain exceptional (above 1-in-100-day) | 8 | 2 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-20 | ERA5 (final) | 76.1 | 6.5 | 24.6 | 6.1 | 23.5 | rain heavy (above 1-in-10-day) | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-21 | ERA5 (final) | 11.4 | 1.7 | 27.3 | 6.9 | 26.3 |  | 8 | 7 | 0 | 8 | 5 | 4 | 0 |
| 2026-03-22 | ERA5 (final) | 28.8 | 3.9 | 24.9 | 7.9 | 25.1 |  | 8 | 1 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-23 | ERA5 (final) | 53.2 | 4.9 | 26.1 | 7.3 | 26.6 | rain heavy (above 1-in-10-day) | 8 | 1 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-24 | ERA5 (final) | 49.7 | 4.7 | 25.3 | 6.7 | 26.9 | rain heavy (above 1-in-10-day) | 8 | 2 | 0 | 8 | 2 | 0 | 0 |
| 2026-03-25 | ERA5 (final) | 124.8 | 13.6 | 24.8 | 7.1 | 26.2 | rain exceptional (above 1-in-100-day) | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-26 | ERA5 (final) | 22.2 | 4.6 | 26.2 | 7.9 | 28.0 |  | 8 | 6 | 0 | 8 | 3 | 0 | 0 |
| 2026-03-27 | ERA5 (final) | 24.4 | 4.2 | 25.8 | 7.2 | 27.4 |  | 8 | 5 | 0 | 8 | 4 | 0 | 0 |
| 2026-03-28 | ERA5 (final) | 29.3 | 3.7 | 24.8 | 6.8 | 25.7 |  | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-29 | ERA5 (final) | 19.4 | 6.7 | 27.1 | 8.0 | 26.7 |  | 8 | 4 | 0 | 8 | 2 | 1 | 0 |
| 2026-03-30 | ERA5 (final) | 19.4 | 3.4 | 26.6 | 6.3 | 27.3 |  | 8 | 1 | 0 | 8 | 0 | 0 | 0 |
| 2026-03-31 | ERA5 (final) | 42.4 | 5.6 | 24.8 | 6.1 | 25.5 |  | 8 | 0 | 0 | 8 | 0 | 0 | 0 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*