# Site weather record · Mbale · June 2026

Site 1.0821, 34.1750. 30 of 30 days recorded, 30 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 438.3 mm against a pro-rata normal of 482 mm (91 % of normal; full-month normal 482 mm, 1991-2020).
- Rain days (1 mm or more): 26 against a pro-rata normal of 27.2.
- Heavy rain days (above the site's 1-in-10-day amount, 32 mm): 4; exceptional (above 1-in-100-day, 79 mm): 0.
- Days with gusts above the 1-in-10-day value (8 m/s): 6; days hotter than the 1-in-10-day maximum (27.4 °C): 7.
- Working hours lost to weather (caution or stop): outdoor labour 5 h, concrete pour 62 h, asphalt & surfacing 178 h, crane lifts 0 h, work at height 105 h, painting & coatings 171 h, earthworks 151 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-06-01 | ERA5 (final) | 23.1 | 3.8 | 27.2 | 6.9 | 27.8 |  | 8 | 5 | 0 | 8 | 3 | 0 | 0 |
| 2026-06-02 | ERA5 (final) | 40.2 | 3.9 | 26.1 | 6.7 | 26.8 | rain heavy (above 1-in-10-day) | 8 | 4 | 0 | 8 | 3 | 0 | 0 |
| 2026-06-03 | ERA5 (final) | 38.1 | 5.3 | 25.3 | 6.4 | 26.3 | rain heavy (above 1-in-10-day) | 8 | 0 | 0 | 8 | 0 | 0 | 0 |
| 2026-06-04 | ERA5 (final) | 18.2 | 3.5 | 27.1 | 5.3 | 27.5 |  | 8 | 6 | 0 | 8 | 2 | 1 | 0 |
| 2026-06-05 | ERA5 (final) | 25.6 | 3.6 | 27.7 | 6.2 | 27.9 | heat above 1-in-10-day | 8 | 6 | 0 | 8 | 3 | 2 | 0 |
| 2026-06-06 | ERA5 (final) | 18.0 | 4.5 | 27.0 | 7.3 | 28.0 |  | 7 | 6 | 1 | 8 | 4 | 0 | 0 |
| 2026-06-07 | ERA5 (final) | 7.6 | 2.3 | 26.8 | 8.5 | 27.5 | gust above 1-in-10-day | 8 | 8 | 4 | 8 | 7 | 6 | 0 |
| 2026-06-08 | ERA5 (final) | 9.7 | 1.9 | 26.9 | 7.5 | 28.2 |  | 7 | 5 | 0 | 8 | 3 | 1 | 4 |
| 2026-06-09 | ERA5 (final) | 5.1 | 1.9 | 26.8 | 7.1 | 27.6 |  | 8 | 7 | 2 | 8 | 6 | 2 | 0 |
| 2026-06-10 | ERA5 (final) | 10.8 | 2.5 | 26.5 | 7.3 | 27.0 |  | 8 | 5 | 2 | 8 | 4 | 1 | 4 |
| 2026-06-11 | ERA5 (final) | 1.6 | 0.8 | 26.9 | 8.1 | 26.4 | gust above 1-in-10-day | 8 | 7 | 4 | 8 | 7 | 4 | 2 |
| 2026-06-12 | ERA5 (final) | 0.7 | 0.2 | 28.2 | 9.2 | 27.1 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 8 | 3 | 8 | 6 | 3 | 8 |
| 2026-06-13 | ERA5 (final) | 10.6 | 3.1 | 26.7 | 8.1 | 28.4 | gust above 1-in-10-day | 7 | 7 | 0 | 8 | 5 | 1 | 5 |
| 2026-06-14 | ERA5 (final) | 16.6 | 3.2 | 25.8 | 7.9 | 27.1 |  | 8 | 2 | 2 | 8 | 2 | 0 | 0 |
| 2026-06-15 | ERA5 (final) | 11.8 | 2.0 | 25.6 | 7.7 | 27.3 |  | 8 | 3 | 0 | 8 | 1 | 0 | 0 |
| 2026-06-16 | ERA5 (final) | 41.1 | 5.6 | 26.9 | 6.3 | 27.5 | rain heavy (above 1-in-10-day) | 8 | 3 | 0 | 8 | 3 | 0 | 0 |
| 2026-06-17 | ERA5 (final) | 2.3 | 0.7 | 26.7 | 8.1 | 25.9 | gust above 1-in-10-day | 8 | 7 | 3 | 8 | 5 | 4 | 6 |
| 2026-06-18 | ERA5 (final) | 4.6 | 1.9 | 26.6 | 7.2 | 26.9 |  | 8 | 7 | 3 | 8 | 6 | 3 | 6 |
| 2026-06-19 | ERA5 (final) | 4.1 | 1.7 | 26.8 | 6.4 | 26.9 |  | 8 | 7 | 1 | 8 | 4 | 1 | 7 |
| 2026-06-20 | ERA5 (final) | 9.4 | 1.9 | 27.4 | 8.2 | 26.7 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 8 | 1 | 8 | 6 | 5 | 6 |
| 2026-06-21 | ERA5 (final) | 4.0 | 1.3 | 26.8 | 7.9 | 26.6 |  | 8 | 7 | 2 | 8 | 5 | 2 | 0 |
| 2026-06-22 | ERA5 (final) | 8.3 | 2.3 | 26.4 | 7.0 | 27.4 |  | 8 | 6 | 0 | 8 | 3 | 0 | 4 |
| 2026-06-23 | ERA5 (final) | 22.1 | 4.7 | 25.3 | 6.8 | 26.7 |  | 8 | 5 | 0 | 8 | 4 | 0 | 0 |
| 2026-06-24 | ERA5 (final) | 74.6 | 11.1 | 27.9 | 6.9 | 26.0 | rain heavy (above 1-in-10-day); heat above 1-in-10-day | 8 | 6 | 3 | 8 | 6 | 5 | 0 |
| 2026-06-25 | ERA5 (final) | 17.1 | 3.6 | 27.0 | 6.9 | 28.1 |  | 7 | 5 | 0 | 8 | 2 | 1 | 0 |
| 2026-06-26 | ERA5 (final) | 0.1 | 0.1 | 28.2 | 6.5 | 26.2 | heat above 1-in-10-day | 8 | 8 | 8 | 8 | 8 | 5 | 8 |
| 2026-06-27 | ERA5 (final) | 0.0 | 0.0 | 27.2 | 7.9 | 25.2 |  | 8 | 8 | 8 | 8 | 8 | 7 | 8 |
| 2026-06-28 | ERA5 (final) | 0.0 | 0.0 | 26.7 | 6.7 | 24.2 |  | 8 | 8 | 8 | 8 | 8 | 7 | 8 |
| 2026-06-29 | ERA5 (final) | 1.1 | 0.6 | 27.5 | 7.8 | 26.1 | heat above 1-in-10-day | 8 | 7 | 5 | 8 | 6 | 5 | 6 |
| 2026-06-30 | ERA5 (final) | 11.8 | 2.8 | 28.3 | 6.7 | 28.3 | heat above 1-in-10-day | 7 | 7 | 2 | 8 | 5 | 3 | 7 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*