# Site weather record · Mbarara · August 2026

Site -0.6072, 30.6545. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 16.6 mm against a pro-rata normal of 46 mm (36 % of normal; full-month normal 46 mm, 1991-2020).
- Rain days (1 mm or more): 8 against a pro-rata normal of 11.2.
- Heavy rain days (above the site's 1-in-10-day amount, 5 mm): 0; exceptional (above 1-in-100-day, 12 mm): 0.
- Days with gusts above the 1-in-10-day value (11 m/s): 6; days hotter than the 1-in-10-day maximum (29.1 °C): 18.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 128 h, asphalt & surfacing 34 h, crane lifts 0 h, work at height 29 h, painting & coatings 31 h, earthworks 5 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-08-01 | ERA5 (final) | 0.3 | 0.2 | 28.8 | 10.4 | 24.3 |  | 8 | 5 | 7 | 8 | 7 | 7 | 8 |
| 2026-08-02 | ERA5 (final) | 1.2 | 0.5 | 27.5 | 6.9 | 23.8 |  | 8 | 8 | 5 | 8 | 7 | 5 | 8 |
| 2026-08-03 | ERA5 (final) | 2.2 | 0.4 | 27.5 | 7.3 | 23.7 |  | 8 | 8 | 3 | 8 | 8 | 5 | 8 |
| 2026-08-04 | ERA5 (final) | 1.1 | 0.4 | 27.6 | 10.4 | 23.2 |  | 8 | 6 | 7 | 8 | 7 | 5 | 8 |
| 2026-08-05 | ERA5 (final) | 2.0 | 0.8 | 26.2 | 8.9 | 23.6 |  | 8 | 6 | 1 | 8 | 5 | 3 | 5 |
| 2026-08-06 | ERA5 (final) | 0.2 | 0.2 | 29.4 | 9.2 | 25.0 | heat above 1-in-10-day | 8 | 4 | 8 | 8 | 8 | 6 | 8 |
| 2026-08-07 | ERA5 (final) | 0.6 | 0.2 | 27.9 | 9.6 | 23.9 |  | 8 | 4 | 3 | 8 | 8 | 6 | 8 |
| 2026-08-08 | ERA5 (final) | 0.1 | 0.1 | 28.2 | 10.3 | 23.5 |  | 8 | 3 | 8 | 8 | 8 | 7 | 8 |
| 2026-08-09 | ERA5 (final) | 0.0 | 0.0 | 29.3 | 10.1 | 23.7 | heat above 1-in-10-day | 8 | 2 | 8 | 8 | 8 | 7 | 8 |
| 2026-08-10 | ERA5 (final) | 0.0 | 0.0 | 29.9 | 9.8 | 24.2 | heat above 1-in-10-day | 8 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-08-11 | ERA5 (final) | 0.1 | 0.1 | 29.8 | 9.9 | 24.5 | heat above 1-in-10-day | 8 | 3 | 7 | 8 | 8 | 8 | 8 |
| 2026-08-12 | ERA5 (final) | 0.0 | 0.0 | 30.5 | 10.3 | 25.0 | heat above 1-in-10-day | 8 | 3 | 8 | 8 | 8 | 7 | 8 |
| 2026-08-13 | ERA5 (final) | 0.0 | 0.0 | 30.4 | 9.8 | 23.9 | heat above 1-in-10-day | 8 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-08-14 | ERA5 (final) | 0.0 | 0.0 | 29.8 | 11.8 | 23.3 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 2 | 8 | 8 | 5 | 8 | 8 |
| 2026-08-15 | ERA5 (final) | 0.0 | 0.0 | 31.1 | 10.4 | 25.2 | heat above 1-in-10-day | 8 | 2 | 8 | 8 | 8 | 8 | 8 |
| 2026-08-16 | ERA5 (final) | 0.0 | 0.0 | 29.1 | 7.4 | 23.7 | heat above 1-in-10-day | 8 | 6 | 8 | 8 | 8 | 8 | 8 |
| 2026-08-17 | ERA5 (final) | 0.0 | 0.0 | 30.3 | 7.9 | 25.0 | heat above 1-in-10-day | 8 | 5 | 8 | 8 | 8 | 8 | 8 |
| 2026-08-18 | ERA5 (final) | 0.2 | 0.1 | 29.2 | 9.5 | 24.5 | heat above 1-in-10-day | 8 | 3 | 7 | 8 | 8 | 8 | 8 |
| 2026-08-19 | ERA5 (final) | 1.5 | 0.8 | 27.4 | 8.2 | 24.3 |  | 8 | 8 | 6 | 8 | 8 | 8 | 8 |
| 2026-08-20 | ERA5 (final) | 1.9 | 1.0 | 25.0 | 9.0 | 22.9 |  | 8 | 7 | 4 | 8 | 7 | 6 | 7 |
| 2026-08-21 | ERA5 (final) | 0.2 | 0.1 | 29.1 | 9.1 | 24.4 | heat above 1-in-10-day | 8 | 5 | 8 | 8 | 8 | 6 | 8 |
| 2026-08-22 | ERA5 (final) | 0.0 | 0.0 | 28.6 | 9.3 | 23.7 |  | 8 | 3 | 8 | 8 | 8 | 8 | 8 |
| 2026-08-23 | ERA5 (final) | 0.4 | 0.2 | 28.2 | 9.4 | 24.3 |  | 8 | 5 | 6 | 8 | 8 | 7 | 8 |
| 2026-08-24 | ERA5 (final) | 1.9 | 1.5 | 28.5 | 10.3 | 24.5 |  | 8 | 4 | 8 | 8 | 8 | 6 | 8 |
| 2026-08-25 | ERA5 (final) | 2.5 | 1.9 | 28.8 | 9.7 | 24.7 |  | 8 | 3 | 6 | 8 | 7 | 7 | 7 |
| 2026-08-26 | ERA5 (final) | 0.2 | 0.2 | 29.6 | 10.7 | 24.7 | heat above 1-in-10-day | 8 | 2 | 8 | 8 | 8 | 7 | 8 |
| 2026-08-27 | ERA5 (final) | 0.0 | 0.0 | 30.7 | 11.5 | 24.7 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 1 | 8 | 8 | 2 | 8 | 8 |
| 2026-08-28 | ERA5 (final) | 0.0 | 0.0 | 29.7 | 11.7 | 24.2 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 1 | 8 | 8 | 5 | 8 | 8 |
| 2026-08-29 | ERA5 (final) | 0.0 | 0.0 | 29.4 | 11.9 | 24.0 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 1 | 8 | 8 | 5 | 8 | 8 |
| 2026-08-30 | ERA5 (final) | 0.0 | 0.0 | 29.7 | 12.1 | 24.3 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 2 | 8 | 8 | 5 | 8 | 8 |
| 2026-08-31 | ERA5 (final) | 0.0 | 0.0 | 29.4 | 11.9 | 24.0 | gust above 1-in-10-day; heat above 1-in-10-day | 8 | 2 | 8 | 8 | 5 | 8 | 8 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*