# Site weather record · Muscat · January 2026

Site 23.5880, 58.3829. 31 of 31 days recorded, 31 finalised from ERA5 (the rest are preliminary model analysis and are replaced automatically once ERA5 is published).

- Rain 2.0 mm against a pro-rata normal of 18 mm (11 % of normal; full-month normal 18 mm, 1991-2020).
- Rain days (1 mm or more): 1 against a pro-rata normal of 2.5.
- Heavy rain days (above the site's 1-in-10-day amount, 1 mm): 1; exceptional (above 1-in-100-day, 12 mm): 0.
- Days with gusts above the 1-in-10-day value (12 m/s): 4; days hotter than the 1-in-10-day maximum (28.5 °C): 1.
- Working hours lost to weather (caution or stop): outdoor labour 0 h, concrete pour 90 h, asphalt & surfacing 14 h, crane lifts 7 h, work at height 24 h, painting & coatings 27 h, earthworks 1 h.

| date | source | rain mm | max mm/h | Tmax °C | gust m/s | WBGT sun °C | flags | go h Outdoor labour | go h Concrete pour | go h Asphalt & surfacing | go h Crane lifts | go h Work at height | go h Painting & coatings | go h Earthworks |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2026-01-01 | ERA5 (final) | 0.0 | 0.0 | 24.3 | 7.3 | 22.1 |  | 9 | 9 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-02 | ERA5 (final) | 0.0 | 0.0 | 24.8 | 6.9 | 23.9 |  | 9 | 9 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-03 | ERA5 (final) | 0.0 | 0.0 | 25.7 | 6.4 | 24.5 |  | 9 | 9 | 9 | 9 | 9 | 7 | 9 |
| 2026-01-04 | ERA5 (final) | 0.0 | 0.0 | 27.1 | 6.9 | 25.2 |  | 9 | 9 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-05 | ERA5 (final) | 0.0 | 0.0 | 26.1 | 8.6 | 23.8 |  | 9 | 6 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-06 | ERA5 (final) | 0.0 | 0.0 | 26.5 | 12.5 | 23.2 | gust above 1-in-10-day | 9 | 4 | 9 | 9 | 7 | 8 | 9 |
| 2026-01-07 | ERA5 (final) | 0.0 | 0.0 | 25.8 | 9.7 | 22.9 |  | 9 | 5 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-08 | ERA5 (final) | 0.0 | 0.0 | 25.2 | 9.3 | 22.9 |  | 9 | 6 | 9 | 9 | 9 | 9 | 9 |
| 2026-01-09 | ERA5 (final) | 0.0 | 0.0 | 26.1 | 11.2 | 22.9 |  | 9 | 5 | 9 | 9 | 7 | 9 | 9 |
| 2026-01-10 | ERA5 (final) | 0.0 | 0.0 | 26.8 | 9.3 | 25.0 |  | 9 | 6 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-11 | ERA5 (final) | 0.2 | 0.1 | 26.4 | 9.0 | 23.8 |  | 9 | 7 | 7 | 9 | 9 | 9 | 9 |
| 2026-01-12 | ERA5 (final) | 0.1 | 0.1 | 25.8 | 9.1 | 24.7 |  | 9 | 8 | 7 | 9 | 9 | 7 | 9 |
| 2026-01-13 | ERA5 (final) | 0.0 | 0.0 | 26.0 | 9.9 | 24.9 |  | 9 | 7 | 9 | 9 | 9 | 7 | 9 |
| 2026-01-14 | ERA5 (final) | 0.0 | 0.0 | 26.9 | 9.9 | 25.8 |  | 9 | 8 | 9 | 9 | 9 | 7 | 9 |
| 2026-01-15 | ERA5 (final) | 0.0 | 0.0 | 27.5 | 9.5 | 26.4 |  | 9 | 6 | 9 | 9 | 9 | 6 | 9 |
| 2026-01-16 | ERA5 (final) | 0.0 | 0.0 | 25.8 | 9.5 | 23.8 |  | 9 | 4 | 9 | 9 | 9 | 9 | 9 |
| 2026-01-17 | ERA5 (final) | 0.0 | 0.0 | 23.9 | 11.7 | 21.1 |  | 9 | 3 | 9 | 9 | 6 | 8 | 9 |
| 2026-01-18 | ERA5 (final) | 0.0 | 0.0 | 24.9 | 9.4 | 21.4 |  | 9 | 5 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-19 | ERA5 (final) | 0.0 | 0.0 | 26.2 | 9.5 | 23.9 |  | 9 | 6 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-20 | ERA5 (final) | 0.0 | 0.0 | 26.9 | 8.5 | 24.4 |  | 9 | 5 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-21 | ERA5 (final) | 0.0 | 0.0 | 28.6 | 12.6 | 23.9 | gust above 1-in-10-day; heat above 1-in-10-day | 9 | 4 | 9 | 9 | 7 | 9 | 9 |
| 2026-01-22 | ERA5 (final) | 0.0 | 0.0 | 22.3 | 15.6 | 19.1 | gust above 1-in-10-day | 9 | 3 | 8 | 4 | 2 | 9 | 9 |
| 2026-01-23 | ERA5 (final) | 0.0 | 0.0 | 21.2 | 7.3 | 18.2 |  | 9 | 9 | 9 | 9 | 9 | 9 | 9 |
| 2026-01-24 | ERA5 (final) | 0.0 | 0.0 | 24.1 | 11.1 | 20.9 |  | 9 | 5 | 9 | 9 | 8 | 9 | 9 |
| 2026-01-25 | ERA5 (final) | 0.0 | 0.0 | 26.5 | 8.2 | 22.5 |  | 9 | 5 | 9 | 9 | 9 | 9 | 9 |
| 2026-01-26 | ERA5 (final) | 0.0 | 0.0 | 25.4 | 13.2 | 22.8 | gust above 1-in-10-day | 9 | 4 | 9 | 7 | 6 | 9 | 9 |
| 2026-01-27 | ERA5 (final) | 1.7 | 0.3 | 23.0 | 8.8 | 21.3 | rain heavy (above 1-in-10-day) | 9 | 9 | 0 | 9 | 7 | 7 | 8 |
| 2026-01-28 | ERA5 (final) | 0.0 | 0.0 | 24.8 | 10.5 | 22.6 |  | 9 | 5 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-29 | ERA5 (final) | 0.0 | 0.0 | 26.3 | 11.6 | 23.2 |  | 9 | 5 | 9 | 9 | 8 | 9 | 9 |
| 2026-01-30 | ERA5 (final) | 0.0 | 0.0 | 27.7 | 10.8 | 25.2 |  | 9 | 6 | 9 | 9 | 9 | 8 | 9 |
| 2026-01-31 | ERA5 (final) | 0.0 | 0.0 | 26.8 | 11.4 | 24.9 |  | 9 | 7 | 9 | 9 | 8 | 8 | 9 |

*How to use this record: under FIDIC 2017 Sub-Clause 8.5 (1999 Sub-Clause 8.4) a contractor may claim time for exceptionally adverse climatic conditions. This record shows how the month compared with the site's own 1991-2020 climate. It is a weather record for the site location, not a site measurement; a site rain gauge and daily diary remain the primary evidence, and the contract's own definition of 'exceptional' governs.*