 "_note": "Typical screening values. The contract specification, the crane manufacturer's limits and the site health-and-safety plan always take precedence. Edit these to match them.",
 "working_hours": [
  8,
  17
 ],
 "heat_wbgt_moderate_work_acclimatised_C": {
  "_source": "ACGIH TLV / ISO 7243 style screening, moderate work, acclimatised workers",
  "continuous": 28.0,
  "work75_rest25": 29.0,
  "work50_rest50": 30.0,
  "work25_rest75": 31.0
 },
 "crane": {
  "_source": "typical tower-crane in-service limits; gust scaled from 10 m to hook height by the 1/7 power law",
  "hook_height_m": 30,
  "gust_caution_ms": 15.0,
  "gust_stop_ms": 20.0,
  "vis_stop_km": 0.5,
  "vis_caution_km": 1.5
 },
 "work_at_height": {
  "gust_caution_ms": 11.0,
  "gust_stop_ms": 15.0,
  "rain_stop_mm_h": 0.2,
  "vis_stop_km": 0.5,
  "vis_caution_km": 1.5
 },
 "concrete": {
  "_source": "ACI 305R evaporation-rate guidance (Uno 1998 formula); concrete assumed warmer than air by concrete_minus_air_C",
  "concrete_minus_air_C": 3.0,
  "evap_caution_kg_m2_h": 0.5,
  "evap_stop_kg_m2_h": 1.0,
  "rain_stop_mm_h": 0.5,
  "rain_prob_caution_pct": 50,
  "rain_prob_stop_pct": 75,
  "cold_stop_C": 5.0,
  "cold_caution_C": 10.0,
  "_cold_source": "ACI 306R cold-weather concreting: protect below about 5 C; caution below 10 C"
 },
 "coatings": {
  "_source": "ISO 8502-4: surface at least 3 C above dew point; RH at most 85 %",
  "dewpoint_margin_stop_C": 3.0,
  "dewpoint_margin_caution_C": 5.0,
  "rh_stop_pct": 85,
  "rh_caution_pct": 80
 },
 "earthworks": {
  "rain_prev24h_caution_mm": 5.0,
  "rain_prev24h_stop_mm": 15.0,
  "rain_stop_mm_h": 1.0
 },
 "lightning": {
  "_source": "convective screening: CAPE with rain probability, and forecast rain in the hour for 'likely'; Kampala CAPE is above 1000 J/kg most hours, so CAPE alone is not a signal. Stop exposed work at the first thunder (30-30 rule).",
  "cape_caution": 1000,
  "cape_stop": 1000,
  "prob_caution_pct": 50,
  "prob_stop_pct": 70,
  "rain_stop_mm_h": 0.5
 },
 "asphalt": {
  "_source": "typical hot-mix asphalt and bituminous surface-dressing practice (e.g. MoWT General Specifications for Roads and Bridges): no laying or spraying in rain or on a wet surface, nor when rain is imminent; thin lifts cool fast in wind",
  "rain_stop_mm_h": 0.1,
  "wet_surface_prev3h_mm": 0.5,
  "rain_prob_next3_caution_pct": 50,
  "rain_prob_next3_stop_pct": 75,
  "min_air_C": 10,
  "wind_caution_ms": 8
 },
 "break_hours": [
  13
 ],
 "_working_note": "8-hour working day: 08:00-17:00 with a lunch break 13:00-14:00 (break hours are not counted)",
 "dust": {
  "_source": "Open-Meteo/CAMS dust concentration; a dust event reduces visibility and needs eye protection and secured materials",
  "dust_warn_ug_m3": 200,
  "pm10_warn_ug_m3": 150
 }
}