Site weather · Cape Town

For contractors and site managers: the next seven days as workable hours per trade, with a short site note, refreshed every morning at 06:00. Every day is also archived, so the record of what the weather did, month by month and compared with the site's 1991-2020 climate, builds up on its own.

Site note · Friday 20 November · issued 05:43

Pour concrete 07-12 h; fast drying limits the rest of the day.

Rain 0 mm · 2%Storms lowHeat (WBGT) 21 °CGusts 15 m/s at hook height
Concrete pourLimited

Go 07-12 h

070809101113141516

Limited by fast drying. Curing cover and windbreaks ready.

Work at heightGo with care

Go with care

070809101113141516

Limited by wind. Work at height with care: watch gusts and the sky.

No weather limitsGo

Outdoor labour, Asphalt & surfacing, Crane lifts, Painting & coatings, Earthworks

Work as planned; keep an eye on the sky.

  • UV index up to 9 (very high): hats with neck cover, long sleeves, sunscreen.

Next days

Saturday 21 November

Some limits today: check your trade below.

Sunday 22 November

Some limits today: check your trade below.

Monday 23 November

Pour concrete 07-12 h; fast drying limits the rest of the day.

Hours are go hours, 07:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.

Seven-day site meteogram

Seven-day site meteogram: heat, rain and storms, wind, sun and cloud, concrete and painting, go hours per trade, daily summary and regional maps

Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour

Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued

Cards to share

The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption

Today's site card The week on site cardHow to read the card

Monthly record

Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.

monthdaysrain mmof normalheavy daysexceptional days concrete h lostlabour (heat) h lostdaily
2026-11131.09 %00670CSV
2026-103127.6103 %40600CSV
2026-093042.1102 %40750CSV
2026-083111.917 %10490CSV
2026-073110.513 %00470CSV
2026-063050.157 %10500CSV
2026-0531127.2236 %13430CSV
2026-043097.9274 %41510CSV
2026-033110.487 %509611CSV
2026-022821.4197 %511010CSV
2026-01313.732 %301490CSV

Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).