Site note · Friday 20 November · issued 06:43

Storms likely from 15:00: finish lifts, roof and asphalt work before then.

Rain 13 mm · 100%Storms likely from 15:00Heat (WBGT) 23 °CGusts 13 m/s at hook height
Concrete pourStop

No window today

0809101112141516

Limited by rain, storms. No pour window: postpone, or pour under cover.

Asphalt & surfacingStop

No window today

0809101112141516

Limited by rain or wet surface, storms. No dry window: do not lay or spray.

Work at heightStop

No window today

0809101112141516

Limited by rain, storms. Keep off roofs and scaffolds.

Painting & coatingsStop

No window today

0809101112141516

Limited by rain, humidity or dew. Too humid or wet for painting and coatings.

EarthworksStop

No window today

0809101112141516

Limited by wet ground, rain. Ground too wet: protect formation, keep plant off soft ground. Ground wet after 14 mm in 24 h.

Crane liftsLimited

Go 08-13 h, 14-15 h

0809101112141516

Limited by storms. Check the anemometer before each lift.

No weather limitsGo

Outdoor labour

Work as planned; keep an eye on the sky.

  • UV index up to 9 (very high): hats with neck cover, long sleeves, sunscreen.

Next days

Saturday 21 November

Storms likely from 14:00: finish lifts, roof and asphalt work before then.

Sunday 22 November

Wet day (12 mm): no concrete or asphalt window.

Monday 23 November

Storms likely from 14:00: finish lifts, roof and asphalt work before then.

Hours are go hours, 08:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.

Seven-day site meteogram

Seven-day site meteogram: heat, rain and storms, wind, sun and cloud, concrete and painting, go hours per trade, daily summary and regional maps

Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour

Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued

Cards to share

The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption

Today's site card The week on site cardHow to read the card

Monthly record

Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.

monthdaysrain mmof normalheavy daysexceptional days concrete h lostlabour (heat) h lostdaily
2026-111350.8141 %10380CSV
2026-103118.045 %001170CSV
2026-093011.873 %40570CSV
2026-08314.019 %00500CSV
2026-07315.945 %00110CSV
2026-06309.122 %00160CSV
2026-053158.564 %2070CSV
2026-043098.786 %21640CSV
2026-0331189.0332 %53540CSV
2026-0228108.0365 %63940CSV
2026-01314.814 %001480CSV

Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).