Site weather · Central Kampala

For contractors and site managers: the next seven days as workable hours per trade, with a short site note, refreshed every morning at 06:00. Every day is also archived, so the record of what the weather did, month by month and compared with the site's 1991-2020 climate, builds up on its own.

Site note · Friday 20 November · issued 06:43

Storms possible from 10:00: do exposed work in the morning.

Rain 2 mm · 59%Storms possible from 10:00Heat (WBGT) 27 °CGusts 8 m/s at hook height
Asphalt & surfacingStop

No window today

0809101112141516

Limited by rain or wet surface, storms. No dry window: do not lay or spray.

Concrete pourLimited

Go 14-17 h

0809101112141516

Limited by rain, storms. Keep covers ready outside this window.

Crane liftsLimited

Go 08-10 h, 14-17 h

0809101112141516

Limited by storms. Check the anemometer before each lift.

Work at heightLimited

Go 09-10 h, 14-17 h

0809101112141516

Limited by storms, rain. Clear roofs and scaffolds before storms.

Painting & coatingsLimited

Go 14-17 h

0809101112141516

Limited by humidity or dew, rain. Check the surface is 3 °C above dew point.

EarthworksLimited

Go 09-13 h, 14-17 h

0809101112141516

Limited by rain. Protect formation and stockpiles.

No weather limitsGo

Outdoor labour

Work as planned; keep an eye on the sky.

  • UV index up to 9 (very high): hats with neck cover, long sleeves, sunscreen.
  • Dust: PM2.5 up to 42 µg/m³; damp down haul roads and cutting work; masks for dusty tasks.

Next days

Saturday 21 November

Wet day (2 mm): no concrete or asphalt window.

Sunday 22 November

Storms likely from 08:00: finish lifts, roof and asphalt work before then.

Monday 23 November

Storms likely from 12:00: finish lifts, roof and asphalt work before then.

Hours are go hours, 08:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.

Seven-day site meteogram

Seven-day site meteogram: heat, rain and storms, wind, sun and cloud, concrete and painting, go hours per trade, daily summary and regional maps

Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour

Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued

Cards to share

The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption

Today's site card The week on site cardHow to read the card

Monthly record

Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.

monthdaysrain mmof normalheavy daysexceptional days concrete h lostlabour (heat) h lostdaily
2026-111393.3120 %30240CSV
2026-1031175.8114 %52450CSV
2026-0930108.790 %70592CSV
2026-083187.881 %12740CSV
2026-073142.551 %00400CSV
2026-063050.844 %20420CSV
2026-0531150.880 %10540CSV
2026-0430163.374 %10590CSV
2026-0331181.6110 %30580CSV
2026-0228153.7148 %41480CSV
2026-013160.356 %00360CSV

Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).

By Gava Charles · Kampala Heat Atlas