Go 07-09 h, 14-15 h
Limited by fast drying, rain. Curing cover and windbreaks ready.
For contractors and site managers: the next seven days as workable hours per trade, with a short site note, refreshed every morning at 06:00. Every day is also archived, so the record of what the weather did, month by month and compared with the site's 1991-2020 climate, builds up on its own.
Site note · Friday 20 November · issued 05:43
Limited by fast drying, rain. Curing cover and windbreaks ready.
Limited by rain or wet surface. Never lay or spray on a wet surface.
Limited by wind. Check the anemometer before each lift.
Limited by wind. Clear roofs and scaffolds before storms.
Limited by humidity or dew. Check the surface is 3 °C above dew point.
Work as planned; keep an eye on the sky.
Next days
Some limits today: check your trade below.
Some limits today: check your trade below.
Pour concrete 13-17 h; rain limits the rest of the day.
Hours are go hours, 07:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.
Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour
Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued
The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption


Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.
| month | days | rain mm | of normal | heavy days | exceptional days | concrete h lost | labour (heat) h lost | daily |
|---|---|---|---|---|---|---|---|---|
| 2026-11 | 13 | 65.7 | 157 % | 2 | 0 | 23 | 4 | CSV |
| 2026-10 | 31 | 64.1 | 72 % | 0 | 1 | 58 | 16 | CSV |
| 2026-09 | 30 | 93.8 | 155 % | 3 | 1 | 58 | 0 | CSV |
| 2026-08 | 31 | 45.8 | 135 % | 2 | 1 | 45 | 4 | CSV |
| 2026-07 | 31 | 63.1 | 149 % | 7 | 0 | 55 | 0 | CSV |
| 2026-06 | 30 | 15.4 | 56 % | 2 | 0 | 17 | 0 | CSV |
| 2026-05 | 31 | 66.4 | 153 % | 5 | 1 | 35 | 2 | CSV |
| 2026-04 | 30 | 49.3 | 67 % | 3 | 0 | 57 | 14 | CSV |
| 2026-03 | 31 | 46.8 | 52 % | 0 | 0 | 52 | 55 | CSV |
| 2026-02 | 28 | 88.4 | 105 % | 3 | 0 | 112 | 107 | CSV |
| 2026-01 | 31 | 40.5 | 44 % | 0 | 0 | 100 | 65 | CSV |
Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).
By Gava Charles · Kampala Heat Atlas