Go 08-12 h
Limited by rain, storms. Keep covers ready outside this window.
For contractors and site managers: the next seven days as workable hours per trade, with a short site note, refreshed every morning at 06:00. Every day is also archived, so the record of what the weather did, month by month and compared with the site's 1991-2020 climate, builds up on its own.
Site note · Friday 20 November · issued 06:43
Limited by rain, storms. Keep covers ready outside this window.
Limited by rain or wet surface, storms. Never lay or spray on a wet surface.
Limited by storms. Check the anemometer before each lift.
Limited by storms, rain. Clear roofs and scaffolds before storms.
Limited by rain, humidity or dew. Check the surface is 3 °C above dew point.
Limited by rain. Protect formation and stockpiles.
Work as planned; keep an eye on the sky.
Next days
Storms possible from 14:00: do exposed work in the morning.
Storms possible from 12:00: do exposed work in the morning.
Storms likely from 15:00: finish lifts, roof and asphalt work before then.
Hours are go hours, 08:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.
Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour
Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued
The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption


Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.
| month | days | rain mm | of normal | heavy days | exceptional days | concrete h lost | labour (heat) h lost | daily |
|---|---|---|---|---|---|---|---|---|
| 2026-11 | 13 | 61.2 | 40 % | 0 | 0 | 24 | 3 | CSV |
| 2026-10 | 31 | 249.1 | 66 % | 1 | 0 | 55 | 6 | CSV |
| 2026-09 | 30 | 96.8 | 35 % | 1 | 0 | 29 | 0 | CSV |
| 2026-08 | 31 | 106.1 | 46 % | 1 | 0 | 36 | 0 | CSV |
| 2026-07 | 31 | 116.8 | 71 % | 1 | 0 | 34 | 0 | CSV |
| 2026-06 | 30 | 51.4 | 29 % | 0 | 0 | 15 | 5 | CSV |
| 2026-05 | 31 | 226.4 | 90 % | 2 | 0 | 54 | 11 | CSV |
| 2026-04 | 30 | 271.6 | 93 % | 2 | 0 | 60 | 5 | CSV |
| 2026-03 | 31 | 227.6 | 114 % | 2 | 0 | 60 | 3 | CSV |
| 2026-02 | 28 | 139.1 | 222 % | 5 | 2 | 40 | 0 | CSV |
| 2026-01 | 31 | 4.2 | 6 % | 0 | 0 | 51 | 1 | CSV |
Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).
By Gava Charles · Kampala Heat Atlas