Site weather · Mbale

For contractors and site managers: the next seven days as workable hours per trade, with a short site note, refreshed every morning at 06:00. Every day is also archived, so the record of what the weather did, month by month and compared with the site's 1991-2020 climate, builds up on its own.

Site note · Friday 20 November · issued 06:43

Storms possible from 14:00: do exposed work in the morning.

Rain 6 mm · 84%Storms possible from 14:00Heat (WBGT) 29 °CGusts 6 m/s at hook height
Outdoor labourLimited

Work/rest cycles

0809101112141516

Work/rest cycles 11-13 h, 14-15 h: at the peak, 45 min work / 15 min rest each hour. Water every 20 min, shade for breaks.

Concrete pourLimited

Go 08-12 h

0809101112141516

Limited by rain, storms. Keep covers ready outside this window.

Asphalt & surfacingLimited

Go 10-12 h

0809101112141516

Limited by rain or wet surface, storms. Never lay or spray on a wet surface.

Crane liftsLimited

Go 08-13 h

0809101112141516

Limited by storms. Check the anemometer before each lift.

Work at heightLimited

Go 08-13 h

0809101112141516

Limited by storms, rain. Clear roofs and scaffolds before storms.

Painting & coatingsLimited

Go 10-13 h

0809101112141516

Limited by rain, humidity or dew. Check the surface is 3 °C above dew point.

EarthworksLimited

Go 08-13 h, 14-15 h, 16-17 h

0809101112141516

Limited by rain. Protect formation and stockpiles.

  • UV index up to 8 (very high): hats with neck cover, long sleeves, sunscreen.
  • Dust: PM2.5 up to 47 µg/m³; damp down haul roads and cutting work; masks for dusty tasks.

Next days

Saturday 21 November

Storms possible from 14:00: do exposed work in the morning.

Sunday 22 November

Storms possible from 11:00: do exposed work in the morning.

Monday 23 November

Storms possible from 14:00: do exposed work in the morning.

Hours are go hours, 08:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.

Seven-day site meteogram

Seven-day site meteogram: heat, rain and storms, wind, sun and cloud, concrete and painting, go hours per trade, daily summary and regional maps

Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour

Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued

Cards to share

The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption

Today's site card The week on site cardHow to read the card

Monthly record

Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.

monthdaysrain mmof normalheavy daysexceptional days concrete h lostlabour (heat) h lostdaily
2026-1113227.657 %10370CSV
2026-10311087.1141 %521498CSV
2026-0930526.9112 %408011CSV
2026-0831243.488 %10585CSV
2026-0731434.6175 %61732CSV
2026-0630438.391 %40625CSV
2026-0531863.7101 %301299CSV
2026-0430983.0103 %501582CSV
2026-03311118.7165 %521632CSV
2026-0228627.1194 %611113CSV
2026-0131131.532 %00901CSV

Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).

By Gava Charles · Kampala Heat Atlas