Go 07-12 h
Limited by fast drying. Curing cover and windbreaks ready.
For contractors and site managers: the next seven days as workable hours per trade, with a short site note, refreshed every morning at 06:00. Every day is also archived, so the record of what the weather did, month by month and compared with the site's 1991-2020 climate, builds up on its own.
Site note · Friday 20 November · issued 07:43
Limited by fast drying. Curing cover and windbreaks ready.
Limited by humidity or dew. Check the surface is 3 °C above dew point.
Work as planned; keep an eye on the sky.
Next days
Pour concrete 07-11 h; fast drying limits the rest of the day.
Some limits today: check your trade below.
Pour concrete 07-12 h; fast drying limits the rest of the day.
Hours are go hours, 07:00-17:00 with lunch excluded; 08-13 means from 08:00 until the lunch break. Screening guidance from a forecast: the contract, crane manufacturer's limits and site H&S plan come first.
Trade panels, the same forecast with only what each trade needs: concrete, asphalt, painting and earthworks · cranes and work at height · heat and outdoor labour
Hourly numbers and per-trade status (CSV) · Thresholds used · Forecasts as issued
The same forecast as images for WhatsApp, LinkedIn, X, Instagram and Facebook, refreshed each morning. Today's briefing · Today (Status / Stories) · Hour-by-hour grid · Printable A4 briefing (PDF) · The week · LinkedIn carousel (PDF) · Caption


Rain against the 1991-2020 normal, heavy and exceptional days, and working hours lost. Days start as preliminary model analysis and are replaced by ERA5 about a week later. Useful as supporting evidence for extension-of-time claims (FIDIC 2017 Sub-Clause 8.5); a site rain gauge and the daily diary remain the primary record.
| month | days | rain mm | of normal | heavy days | exceptional days | concrete h lost | labour (heat) h lost | daily |
|---|---|---|---|---|---|---|---|---|
| 2026-11 | 13 | 0.2 | 16 % | 13 | 0 | 56 | 32 | CSV |
| 2026-10 | 31 | 1.7 | 157 % | 30 | 1 | 196 | 216 | CSV |
| 2026-09 | 30 | 0.0 | – | 30 | 0 | 234 | 231 | CSV |
| 2026-08 | 31 | 1.4 | 133 % | 31 | 0 | 256 | 265 | CSV |
| 2026-07 | 31 | 0.1 | 4 % | 31 | 0 | 261 | 263 | CSV |
| 2026-06 | 30 | 0.0 | – | 30 | 0 | 252 | 238 | CSV |
| 2026-05 | 31 | 0.0 | – | 31 | 0 | 251 | 165 | CSV |
| 2026-04 | 30 | 12.3 | 234 % | 29 | 1 | 174 | 58 | CSV |
| 2026-03 | 31 | 148.7 | 899 % | 6 | 4 | 184 | 2 | CSV |
| 2026-02 | 28 | 0.1 | 1 % | 0 | 0 | 121 | 0 | CSV |
| 2026-01 | 31 | 2.2 | 15 % | 1 | 0 | 93 | 0 | CSV |
Screening guidance from a weather forecast, not an instruction. The contract specification, crane manufacturer's limits and site health-and-safety plan take precedence. Forecast and ERA5 data: Open-Meteo (open-meteo.com, CC BY 4.0).
By Gava Charles · Kampala Heat Atlas